The fracked methane started flowing some time in June or July 2017
- 2017-06-15: Sabal Trail and FSC are in service, claims FPL in the Palm Beach Post. 
- 2017-06-20: Sabal Trail to FERC: “service on the certain Phase I Project facilities commenced on June 14, 2017” 
- 2017-06-30: One compressor unit online at  head of the snake in Alexander City, AL 2017-06-23 
- 2017-07-04: Sabal Trail PR says it’s in service
-  2017-07-11: More fracked methane from the head of the snake. 
- “the remaining Phase I Hillabee Expansion Project facilities…” commenced 2017-07-03