WWALS Watershed Coalition, Inc. (WWALS) is Suwannee RIVERKEEPER® WWALS advocates for conservation and stewardship of the surface waters and groundwater of the Suwannee River Basin and Estuary, in south Georgia and north Florida, among them the Withlacoochee, Willacoochee, Alapaha, Little, Santa Fe, and Suwannee River watersheds, through education, awareness, environmental monitoring, and citizen activities.

WWALS
Home

Datacenter Discussion @ Columbia County Commission 2026-07-23 [Up]

You can help with clean, swimmable, fishable, drinkable, water in the 10,000-square-mile Suwannee River Basin in Florida and Georgia by becoming a WWALS member today!

Pictures

MMM

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

[Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL]
Datacenter Discussion @ Columbia County Commission, 5:30 PM, Thur4sday, 2026-07-23, 372 W Duval Street, Lake City, FL

AG

[Agenda: (1) Data Center Discussion (p.1)]
Agenda: (1) Data Center Discussion (p.1)
PDF

[Page 002 is blank]
Page 002 is blank
PDF

[AGENDA ITEM REQUEST FORM: Data Center Discussion]
AGENDA ITEM REQUEST FORM: Data Center Discussion
PDF

DCCIR

[Data Center Community Impact Resources]
Data Center Community Impact Resources
PDF

[Page 005]
Page 005
PDF

NS

[HOW DATA CENTERS SUPPORT U.S. NATIONAL SECURITY]
HOW DATA CENTERS SUPPORT U.S. NATIONAL SECURITY
PDF

EC

[Economic Contributions of Data Centers in the United States 2023 - 2024, 2026-05-01 --The Data Center Coalition]
Economic Contributions of Data Centers in the United States 2023 - 2024, 2026-05-01 --The Data Center Coalition
PDF

[Page 008]
Page 008
PDF

[Page 009]
Page 009
PDF

[Page 010]
Page 010
PDF

Execsum

[Executive summary]
Executive summary
PDF

[Page 012]
Page 012
PDF

[Page 013]
Page 013
PDF

[Page 014]
Page 014
PDF

I.Intro

[I. Introduction]
I. Introduction
PDF

II.IO

[II. Industry overview]
II. Industry overview
PDF

[Page 017]
Page 017
PDF

III.EC

[III. Economic contribution]
III. Economic contribution
PDF

USR

[U.S. results]
U.S. results
PDF

[Page 020]
Page 020
PDF

[Page 021]
Page 021
PDF

[Page 022]
Page 022
PDF

[Page 023]
Page 023
PDF

SR

[State results]
State results
PDF

[Page 025]
Page 025
PDF

[Page 026]
Page 026
PDF

[Page 027]
Page 027
PDF

[Page 028]
Page 028
PDF

[Page 029]
Page 029
PDF

[Page 030]
Page 030
PDF

[Page 031]
Page 031
PDF

[Page 032]
Page 032
PDF

[Page 033]
Page 033
PDF

IVConc

[IV. Conclusion]
IV. Conclusion
PDF

AppA

[Appendix A: detailed state results]
Appendix A: detailed state results
PDF

[Page 036]
Page 036
PDF

[Page 037]
Page 037
PDF

[Page 038]
Page 038
PDF

[Page 039]
Page 039
PDF

[Page 040]
Page 040
PDF

[Page 041]
Page 041
PDF

[Page 042]
Page 042
PDF

[Page 043]
Page 043
PDF

[Page 044]
Page 044
PDF

[Page 045]
Page 045
PDF

[Page 046]
Page 046
PDF

[Page 047]
Page 047
PDF

[Page 048]
Page 048
PDF

[Page 049]
Page 049
PDF

[Page 050]
Page 050
PDF

[Page 051]
Page 051
PDF

[Page 052]
Page 052
PDF

[Page 053]
Page 053
PDF

[Page 054]
Page 054
PDF

[Page 055]
Page 055
PDF

[Page 056]
Page 056
PDF

[Page 057]
Page 057
PDF

[Page 058]
Page 058
PDF

[Page 059]
Page 059
PDF

[Page 060]
Page 060
PDF

[Page 061]
Page 061
PDF

[Page 062]
Page 062
PDF

[Page 063]
Page 063
PDF

[Page 064]
Page 064
PDF

[Page 065]
Page 065
PDF

[Page 066]
Page 066
PDF

[Page 067]
Page 067
PDF

[Page 068]
Page 068
PDF

[Page 069]
Page 069
PDF

[Page 070]
Page 070
PDF

[Page 071]
Page 071
PDF

[Page 072]
Page 072
PDF

[Page 073]
Page 073
PDF

[Page 074]
Page 074
PDF

[Page 075]
Page 075
PDF

[Page 076]
Page 076
PDF

[Page 077]
Page 077
PDF

[Page 078]
Page 078
PDF

[Page 079]
Page 079
PDF

[Page 080]
Page 080
PDF

[Page 081]
Page 081
PDF

[Page 082]
Page 082
PDF

[Page 083]
Page 083
PDF

[Page 084]
Page 084
PDF

[Page 085]
Page 085
PDF

[Page 086]
Page 086
PDF

[Page 087]
Page 087
PDF

[Page 088]
Page 088
PDF

[Page 089]
Page 089
PDF

[Page 090]
Page 090
PDF

[Page 091]
Page 091
PDF

[Page 092]
Page 092
PDF

[Page 093]
Page 093
PDF

[Page 094]
Page 094
PDF

[Page 095]
Page 095
PDF

[Page 096]
Page 096
PDF

[Page 097]
Page 097
PDF

AppB

[Appendix B: Data sources and methodology for economic contribution]
Appendix B: Data sources and methodology for economic contribution
PDF

[Page 099]
Page 099
PDF

[Page 100]
Page 100
PDF

[Page 101]
Page 101
PDF

[Page 102]
Page 102
PDF

TaDC

[The Truth about Data Centers --DataBank Data Center Evolved]
The Truth about Data Centers --DataBank Data Center Evolved
PDF

[Page 104]
Page 104
PDF

[Page 105]
Page 105
PDF

[Page 106]
Page 106
PDF

[Page 107]
Page 107
PDF

[Page 108]
Page 108
PDF

[Page 109]
Page 109
PDF

[Page 110]
Page 110
PDF

[Page 111]
Page 111
PDF

[Page 112]
Page 112
PDF

PG

[Fossil fuel power generation is highly water-intensive, while wind and solar consume virtually none. As data centers drive the adoption of more renewable energy sources, their indirect water footprint shrinks alongside their carbon footprint — a benefit that is real but rarely reflected in the figures critics cite.]
Fossil fuel power generation is highly water-intensive, while wind and solar consume virtually none. As data centers drive the adoption of more renewable energy sources, their indirect water footprint shrinks alongside their carbon footprint — a benefit that is real but rarely reflected in the figures critics cite.
PDF

[Page 114]
Page 114
PDF

[Page 115]
Page 115
PDF

[Page 116]
Page 116
PDF

[Page 117]
Page 117
PDF

NP

[Data centers are not perfect. They consume real resources, they require real land, and their development affects real communities. None of that is in dispute.]
Data centers are not perfect. They consume real resources, they require real land, and their development affects real communities. None of that is in dispute.
PDF

[Page 119]
Page 119
PDF

USDCREU

[U.S. Data Centers and Responsible Energy Use --Data Center Coalition]
U.S. Data Centers and Responsible Energy Use --Data Center Coalition
PDF

[Page 121]
Page 121
PDF

[Page 122]
Page 122
PDF

[Page 123]
Page 123
PDF

DCWU

[Data Centers and Water Use --Data Center Coalition]
Data Centers and Water Use --Data Center Coalition
PDF

[Key Context for Data Center Cooling & Associated Water Use --Data Center Coalition]
Key Context for Data Center Cooling & Associated Water Use --Data Center Coalition
PDF

EST

[An Energy System in Transition: New Report Identifies the 5 Key Drivers of U.S. Electricity Prices --Data Center Coalition]
An Energy System in Transition: New Report Identifies the 5 Key Drivers of U.S. Electricity Prices --Data Center Coalition
PDF

[Page 127]
Page 127
PDF

[Page 128]
Page 128
PDF

PIDCD

[Potential Impacts of Data Center Development on Florida Communities: Issues for State and Local Policymakers, 2026-01-01 --1000 Friends of Florida]
Potential Impacts of Data Center Development on Florida Communities: Issues for State and Local Policymakers, 2026-01-01 --1000 Friends of Florida
PDF

[Energy Demand: A typical AI-focused data center consumes as much electricity as 100,000 households. The larger data centers now under construction are expected to use 20 times as much., 2026-01-01 --1000 Friends of Florida]
Energy Demand: A typical AI-focused data center consumes as much electricity as 100,000 households. The larger data centers now under construction are expected to use 20 times as much., 2026-01-01 --1000 Friends of Florida
PDF

[Graph: Electricity Consumption at U.S. Data Centers is Expected to More Than Double by 2030 Total electricity consumption by U.S. data centers (terawatt-hours), 2026-01-01 --1000 Friends of Florida]
Graph: Electricity Consumption at U.S. Data Centers is Expected to More Than Double by 2030 Total electricity consumption by U.S. data centers (terawatt-hours), 2026-01-01 --1000 Friends of Florida
PDF

[Page 132]
Page 132
PDF

[Page 133]
Page 133
PDF

[Page 134]
Page 134
PDF

[Page 135]
Page 135
PDF

[Page 136]
Page 136
PDF

LLF

[FPL Large Load Framework, 2026-06-01 --FPL]
FPL Large Load Framework, 2026-06-01 --FPL
PDF

[Page 138]
Page 138
PDF

[Page 139]
Page 139
PDF

[State of Florida Sales tax exemption for data centers over 100 MW]
State of Florida Sales tax exemption for data centers over 100 MW
PDF

[FPL's terms and conditions for large load and high load factor projects are intended to protect the general body of customers]
FPL's terms and conditions for large load and high load factor projects are intended to protect the general body of customers
PDF

[FPL's Large Load Framework leads the nation in customer protections]
FPL's Large Load Framework leads the nation in customer protections
PDF

[FPL has established a process to onboard large load customers]
FPL has established a process to onboard large load customers
PDF

JAX

[Land Use Categories and Zoning Districts Allowing Large-Scale Data Centers, 2026-04-16 --City of Jacksonville Planning Department]
Land Use Categories and Zoning Districts Allowing Large-Scale Data Centers, 2026-04-16 --City of Jacksonville Planning Department
PDF

[Page 145]
Page 145
PDF

[Page 146]
Page 146
PDF

SB484

[Committee Substitute for Senate Bill No. 484: An act relating to data centers; creating s. 163.326, F.S.; providing....]
Committee Substitute for Senate Bill No. 484: An act relating to data centers; creating s. 163.326, F.S.; providing....
PDF

[Page 148]
Page 148
PDF

[Page 149]
Page 149
PDF

[Page 150]
Page 150
PDF

[Page 151]
Page 151
PDF

[Page 152]
Page 152
PDF

[Page 153]
Page 153
PDF

LGDCD

[Local Guidelines for Data Center Development, 2024-01-01 --ULI Americas Data Center Product Council]
Local Guidelines for Data Center Development, 2024-01-01 --ULI Americas Data Center Product Council
PDF

[Page 155]
Page 155
PDF

[Page 156]
Page 156
PDF

[Page 157]
Page 157
PDF

[Page 158]
Page 158
PDF

1.Intro

[1. Introduction: data centers 101, 2024-01-01 --ULI Americas Data Center Product Council]
1. Introduction: data centers 101, 2024-01-01 --ULI Americas Data Center Product Council
PDF

[Graph: Global data created annually in zettabytes, 2024-01-01 --ULI Americas Data Center Product Council]
Graph: Global data created annually in zettabytes, 2024-01-01 --ULI Americas Data Center Product Council
PDF

[Hyperscale data centers are built for a single customer: one of the large tech companies that provide many of the services we use every day—Google (Google Cloud), Amazon (AWS), Microsoft, and Meta. These companies sometimes own their own centers, and sometimes they lease them from a third-party developer. These centers are built based on the data demands of the hyperscaler., 2024-01-01 --ULI Americas Data Center Product Council]
Hyperscale data centers are built for a single customer: one of the large tech companies that provide many of the services we use every day—Google (Google Cloud), Amazon (AWS), Microsoft, and Meta. These companies sometimes own their own centers, and sometimes they lease them from a third-party developer. These centers are built based on the data demands of the hyperscaler., 2024-01-01 --ULI Americas Data Center Product Council
PDF

[Page 162]
Page 162
PDF

[Page 163]
Page 163
PDF

2.what

[2. What happens when data centers come to your region: opportunities, challenges, and mitigations, 2024-01-01 --ULI Americas Data Center Product Council]
2. What happens when data centers come to your region: opportunities, challenges, and mitigations, 2024-01-01 --ULI Americas Data Center Product Council
PDF

[Graph: Growing global data center demand in gigawatts, 2024-01-01 --ULI Americas Data Center Product Council]
Graph: Growing global data center demand in gigawatts, 2024-01-01 --ULI Americas Data Center Product Council
PDF

[Page 166]
Page 166
PDF

[Page 167]
Page 167
PDF

[Page 168]
Page 168
PDF

[Page 169]
Page 169
PDF

[Page 170]
Page 170
PDF

3.Long

[3. Long-term planning for data centers]
3. Long-term planning for data centers
PDF

[Page 172]
Page 172
PDF

4.Reg

[4. Regulating data centers]
4. Regulating data centers
PDF

5.Model

[5 Model zoning ordinance guidelines]
5 Model zoning ordinance guidelines
PDF

[Page 175]
Page 175
PDF

A.App

[6. Appendix, contacts, and additional resources]
6. Appendix, contacts, and additional resources
PDF

[Page 177]
Page 177
PDF

[Page 178]
Page 178
PDF

7.Gloss

[7. Glossary]
7. Glossary
PDF

UDRER

[Understanding the Drivers of Rising Electricity Rates and the Role of Data Centers, 2026-05-01 --Energy+Environmental Economics]
Understanding the Drivers of Rising Electricity Rates and the Role of Data Centers, 2026-05-01 --Energy+Environmental Economics
PDF

[Page 181]
Page 181
PDF

[Page 182]
Page 182
PDF

[Page 183]
Page 183
PDF

[Page 184]
Page 184
PDF

[Page 185]
Page 185
PDF

PHMW

[Primer: How Power Markets Work, 2026-05-01 --Energy+Environmental Economics]
Primer: How Power Markets Work, 2026-05-01 --Energy+Environmental Economics
PDF

[Page 187]
Page 187
PDF

[Page 188]
Page 188
PDF

[Page 189]
Page 189
PDF

[Graph: Figure 3: Cumulative Counts of New Large Load Tariffs by Customer Protection Measures, by Active Year, 2026-05-01 --Energy+Environmental Economics]
Graph: Figure 3: Cumulative Counts of New Large Load Tariffs by Customer Protection Measures, by Active Year, 2026-05-01 --Energy+Environmental Economics
PDF

[Page 191]
Page 191
PDF

[Page 192]
Page 192
PDF

[Page 193]
Page 193
PDF

[Page 194]
Page 194
PDF

WDS

[What the Data Shows: Data Center Rate Impacts to Date, 2026-05-01 --Energy+Environmental Economics]
What the Data Shows: Data Center Rate Impacts to Date, 2026-05-01 --Energy+Environmental Economics
PDF

[Page 196]
Page 196
PDF

[Page 197]
Page 197
PDF

[Page 198]
Page 198
PDF

[Page 199]
Page 199
PDF

DriversRER

[Drivers of Rising Electricity Rates, 2026-05-01 --Energy+Environmental Economics]
Drivers of Rising Electricity Rates, 2026-05-01 --Energy+Environmental Economics
PDF

[Page 201]
Page 201
PDF

[Page 202]
Page 202
PDF

[Page 203]
Page 203
PDF

[Page 204]
Page 204
PDF

[Page 205]
Page 205
PDF

[Page 206]
Page 206
PDF

[Page 207]
Page 207
PDF

GO

[Georgia Overview, 2026-05-01 --Energy+Environmental Economics]
Georgia Overview, 2026-05-01 --Energy+Environmental Economics
PDF

[Page 209]
Page 209
PDF

[Page 210]
Page 210
PDF

[Page 211]
Page 211
PDF

[Page 212]
Page 212
PDF

[Conclusion]
Conclusion
PDF

[Appendix]
Appendix
PDF

[Page 215]
Page 215
PDF

[Page 216]
Page 216
PDF

[Page 217]
Page 217
PDF

MllageR

[AGENDA ITEM REQUEST FORM: Approve adopting the FY 2026-2027 Millage Rate at 7.8150]
AGENDA ITEM REQUEST FORM: Approve adopting the FY 2026-2027 Millage Rate at 7.8150
PDF

[Page 219]
Page 219
PDF

[Page 220]
Page 220
PDF

IPMillageR

[AGENDA ITEM REQUEST FORM: Approve adopting the Columbia County Industrial Park FY 2026-2027 Millage Rate at 7.8150]
AGENDA ITEM REQUEST FORM: Approve adopting the Columbia County Industrial Park FY 2026-2027 Millage Rate at 7.8150
PDF

[Page 222]
Page 222
PDF

[Page 223]
Page 223
PDF