Here’s a bit more about the Water First North Florida (WFNF) billion dollar project to pipe treated wastewater from Jacksonville into the Suwannee River Basin.

The Suwannee River Water Management District (SRWMD) seems to know surprisingly little about this joint project with the St Johns River Water Management District (SJRWMD).

They don’t know where the water would go into wetlands to “clean” it up some more, and they don’t know where it would go to infiltrate into the Floridan Aquifer.

They don’t have a pilot study and they don’t have wetland site assessments.

Turns out there are a couple of reasons why SRWMD does not know or have those things. But I have found out a few things.

And I have leads to find out much more.

[Water First North Florida wetland locations: unknown, No Pilot Study or Wetland Assessments, But here is the RFQ --SRWMD]
Water First North Florida wetland locations: unknown, No Pilot Study or Wetland Assessments, But here is the RFQ –SRWMD

Back on July 8, 2025, SRWMD Deputy Executive Director of Water Resources Amy Brown gave her board a Lower Santa Fe and Ichetucknee Project Update. It included a few slides on the WFNF, aka North Florida Regional Recharge Project.

[North Florida Regional Recharge Project - Conceptualization, 2025-07-08 --SRWMD]
North Florida Regional Recharge Project – Conceptualization, 2025-07-08 –SRWMD
PDF

I noticed one of those slides seemed to designate specific locations for “Potential treatment wetland locations” and “Potential recharge locations.”

[WATER FIRST NORTH FLORIDA, Potential treatment wetland locations and recharge locations, 2025-07-08 --SRWMD]
WATER FIRST NORTH FLORIDA, Potential treatment wetland locations and recharge locations, 2025-07-08 –SRWMD
PDF

So I sent a public records request asking for names and GPS locations.

Their answer: they don’t know the locations.

Slide number 16 was presented as a conceptual graphic. The SRWMD does not have GPS locations of the points on the graphic.

This conceptual graphic has since been updated, shown at the link provided. https://waterfirstnorthfl.com/

Let me know if you have any additional questions.

Here is that revised map, which is much vaguer about locations.

[Wetlands and Recharge Locations, 2025-12-18 --Water First North Florida]
Wetlands and Recharge Locations, 2025-12-18 –Water First North Florida

I noticed another slides said “Next Steps” with pictures labeled “Pilot Study,” “Siting Study RFQ,” and “Wetland Site Assessment.”

[Water First North Florida, Next Steps: Pilot Study, Siting Study RFQ, Wetland Site Assessment, 2025-07-08 --SRWMD]
Water First North Florida, Next Steps: Pilot Study, Siting Study RFQ, Wetland Site Assessment, 2025-07-08 –SRWMD
PDF

Since five months had passed since November, I figured they must have some of that by now. So I sent a public records request for those things.

Their response:

Attached is the SJRWMD RFQ 41325. The SRWMD does not have the pilot study or the wetland site assessments.

The RFQ clarifies some things, and opens more questions.

Here’s a clue as to why SRWMD seems to know little about this project (pages 1-2 of the RFQ):

[North Florida Recharge Project Treatment Wetland and Recharge Facility Investigation, Selection and Conceptual Design RFQ 41325, 2025-07-28 --SJRWMD Governing Board RFQ 41325]
North Florida Recharge Project Treatment Wetland and Recharge Facility Investigation, Selection and Conceptual Design RFQ 41325, 2025-07-28 –SJRWMD Governing Board RFQ 41325
PDF

A District Evaluation Committee (“Committee”) will review and evaluate the Respondents’ qualifications and Project approach, finalize the initial ranking of firms, and determine a shortlist of Respondents.

The Committee will be composed of voting members, all of whom are District employees, and non-voting members, as designated by the following entities (“Project Partners”):

  • Suwannee River Water Management District
  • Clay County Utility Authority
  • Gainesville Regional Utilities
  • JEA
  • St. Johns County Utility Department

SRWMD is just a non-voting committee member, on a par with GRU and JEA.

[The District will conduct the RFQ process as follows:, 2025-07-28 --SJRWMD RFQ 41325]
The District will conduct the RFQ process as follows:, 2025-07-28 –SJRWMD RFQ 41325
PDF

There’s also this cryptic sentence:

Respondents should note that the Cone of Silence provisions set forth in Paragraph 3 of this solicitation applies equally to the Project Partners.

OK, what’s that?

  1. CONTRACT ADMINISTRATION & CONE OF SILENCE

    All inquiries related to this solicitation may only be directed to the Contracts Manager:

    Kendall Siemiatkoski, Contracts Manager
    Phone: (386) 312-2324
    Email: ksiemiat@sjrwmd.com

    Between the release of this solicitation and the posting of the notice of intended decision, Respondents to this solicitation or persons acting on their behalf may not contact any employee or officer of the District or its Project Partners concerning any aspect of this solicitation, except the procurement employee listed above. Violation of this Cone of Silence provision is grounds for rejecting a response.

[3. CONTRACT ADMINISTRATION & CONE OF SILENCE, 2025-07-28 --SJRWMD RFQ 41325]
3. CONTRACT ADMINISTRATION & CONE OF SILENCE, 2025-07-28 –SJRWMD RFQ 41325
PDF

So we have several tax-paid public agencies told not to speak about this project.

Until “the posting of the notice of intended decision,” which has already happened by now.

The District will conduct the RFQ process as follows:

Date Description
June 26, 2025, 1:00 p.m. Pre-Submittal Conference (District HQ – In person, or by phone or web conferencing)
July 28, 2025, 2:00 p.m. Qualifications Submittals due
August 11, 2025, 1:00 p.m. Committee meets to complete its review of the Submittals and will select not less than three Respondents deemed most highly qualified (District HQ, 4049 Reid St., Palatka, FL 32177, Conf. Rm. 147, Admin. Bldg.) One or more members of the Committee may participate via communications media technology through phone or web conferencing.
August 12, 2025 District Issues Notice of Intended Decision (NOID) notifying Respondents of Rankings
September 9, 2025 District Governing Board consideration to approve a ranking of designated firms and competitive negotiations be instituted
September 10, 2025 District enters negotiations with respondents in ranked order

[The District will conduct the RFQ process as follows:, 2025-07-28 --SJRWMD RFQ 41325]
The District will conduct the RFQ process as follows:, 2025-07-28 –SJRWMD RFQ 41325
PDF

That schedule and the RFQ clarifies why SRWMD does not have a pilot study or wetland site assessments. The consultant is supposed to do those things, and the consultant has apparently only recently been selected.

For who imposed that Cone of Silence, and generally who is running the show, see who issued this RFQ: SJRWMD.

Stay tuned for information from SJRWMD.

Images of the rest of the RFQ are below.

 -jsq, John S. Quarterman, Suwannee RIVERKEEPER®

You can help with clean, swimmable, fishable, drinkable, water in the 10,000-square-mile Suwannee River Basin in Florida and Georgia by becoming a WWALS member today!
https://wwals.net/donations/

[SUBMITTAL CHECKLIST, 2025-07-28 --SJRWMD RFQ 41325]
SUBMITTAL CHECKLIST, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Table of Contents, 2025-07-28 --SJRWMD RFQ 41325]
Table of Contents, 2025-07-28 –SJRWMD RFQ 41325
PDF

[3. CONTRACT ADMINISTRATION & CONE OF SILENCE, 2025-07-28 --SJRWMD RFQ 41325]
3. CONTRACT ADMINISTRATION & CONE OF SILENCE, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 6, 2025-07-28 --SJRWMD RFQ 41325]
Page 6, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 7, 2025-07-28 --SJRWMD RFQ 41325]
Page 7, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 8, 2025-07-28 --SJRWMD RFQ 41325]
Page 8, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 9, 2025-07-28 --SJRWMD RFQ 41325]
Page 9, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 10, 2025-07-28 --SJRWMD RFQ 41325]
Page 10, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 11, 2025-07-28 --SJRWMD RFQ 41325]
Page 11, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 12, 2025-07-28 --SJRWMD RFQ 41325]
Page 12, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 13, 2025-07-28 --SJRWMD RFQ 41325]
Page 13, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 14, 2025-07-28 --SJRWMD RFQ 41325]
Page 14, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 15, 2025-07-28 --SJRWMD RFQ 41325]
Page 15, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 16, 2025-07-28 --SJRWMD RFQ 41325]
Page 16, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 17, 2025-07-28 --SJRWMD RFQ 41325]
Page 17, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 18, 2025-07-28 --SJRWMD RFQ 41325]
Page 18, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 19, 2025-07-28 --SJRWMD RFQ 41325]
Page 19, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 20, 2025-07-28 --SJRWMD RFQ 41325]
Page 20, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 21, 2025-07-28 --SJRWMD RFQ 41325]
Page 21, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 22, 2025-07-28 --SJRWMD RFQ 41325]
Page 22, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 23, 2025-07-28 --SJRWMD RFQ 41325]
Page 23, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 24, 2025-07-28 --SJRWMD RFQ 41325]
Page 24, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 25, 2025-07-28 --SJRWMD RFQ 41325]
Page 25, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 26, 2025-07-28 --SJRWMD RFQ 41325]
Page 26, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 27, 2025-07-28 --SJRWMD RFQ 41325]
Page 27, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 28, 2025-07-28 --SJRWMD RFQ 41325]
Page 28, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 29, 2025-07-28 --SJRWMD RFQ 41325]
Page 29, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 30, 2025-07-28 --SJRWMD RFQ 41325]
Page 30, 2025-07-28 –SJRWMD RFQ 41325
PDF

DACons

[DRAFT AGREEMENT BETWEEN THE ST. JOHNS RIVER WATER MANAGEMENT DISTRICT AND CONSULTANT FOR THE NORTH FLORIDA RECHARGE PROJECT TREATMENT WETLAND AND RECHARGE FACILITY INVESTIGATION, SELECTION AND CONCEPTUAL DESIGN PROJECT, 2025-07-28 --SJRWMD RFQ 41325]
DRAFT AGREEMENT BETWEEN THE ST. JOHNS RIVER WATER MANAGEMENT DISTRICT AND CONSULTANT FOR THE NORTH FLORIDA RECHARGE PROJECT TREATMENT WETLAND AND RECHARGE FACILITY INVESTIGATION, SELECTION AND CONCEPTUAL DESIGN PROJECT, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 32, 2025-07-28 --SJRWMD RFQ 41325]
Page 32, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 33, 2025-07-28 --SJRWMD RFQ 41325]
Page 33, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 34, 2025-07-28 --SJRWMD RFQ 41325]
Page 34, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 35, 2025-07-28 --SJRWMD RFQ 41325]
Page 35, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 36, 2025-07-28 --SJRWMD RFQ 41325]
Page 36, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 37, 2025-07-28 --SJRWMD RFQ 41325]
Page 37, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 38, 2025-07-28 --SJRWMD RFQ 41325]
Page 38, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 39, 2025-07-28 --SJRWMD RFQ 41325]
Page 39, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 40, 2025-07-28 --SJRWMD RFQ 41325]
Page 40, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 41, 2025-07-28 --SJRWMD RFQ 41325]
Page 41, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 42, 2025-07-28 --SJRWMD RFQ 41325]
Page 42, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 43, 2025-07-28 --SJRWMD RFQ 41325]
Page 43, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 44, 2025-07-28 --SJRWMD RFQ 41325]
Page 44, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 45, 2025-07-28 --SJRWMD RFQ 41325]
Page 45, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 46, 2025-07-28 --SJRWMD RFQ 41325]
Page 46, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 47, 2025-07-28 --SJRWMD RFQ 41325]
Page 47, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 48, 2025-07-28 --SJRWMD RFQ 41325]
Page 48, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 49, 2025-07-28 --SJRWMD RFQ 41325]
Page 49, 2025-07-28 –SJRWMD RFQ 41325
PDF

AttA

[ATTACHMENT A —STATEMENT OF WORK, 2025-07-28 --SJRWMD RFQ 41325]
ATTACHMENT A —STATEMENT OF WORK, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Location Map, 2025-07-28 --SJRWMD RFQ 41325]
Location Map, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Identification of potential recharge well sites., 2025-07-28 --SJRWMD RFQ 41325]
Identification of potential recharge well sites., 2025-07-28 –SJRWMD RFQ 41325
PDF

[identification of potential RIB and/or recharge wetland sites., 2025-07-28 --SJRWMD RFQ 41325]
identification of potential RIB and/or recharge wetland sites., 2025-07-28 –SJRWMD RFQ 41325
PDF

[Task 4 – Preliminary Candidate Site Identification and Screening, 2025-07-28 --SJRWMD RFQ 41325]
Task 4 – Preliminary Candidate Site Identification and Screening, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Task 5 – Tabletop Site Evaluation of Candidate Sites, 2025-07-28 --SJRWMD RFQ 41325]
Task 5 – Tabletop Site Evaluation of Candidate Sites, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Task 6 – Technical Memoranda, Final Report and Power Point Presentations, 2025-07-28 --SJRWMD RFQ 41325]
Task 6 – Technical Memoranda, Final Report and Power Point Presentations, 2025-07-28 –SJRWMD RFQ 41325
PDF

[B. Annual Spending Plan, 2025-07-28 --SJRWMD RFQ 41325]
B. Annual Spending Plan, 2025-07-28 –SJRWMD RFQ 41325
PDF

AttB

[ATTACHMENT B — INSURANCE REQUIREMENTS, 2025-07-28 --SJRWMD RFQ 41325]
ATTACHMENT B — INSURANCE REQUIREMENTS, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 59, 2025-07-28 --SJRWMD RFQ 41325]
Page 59, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 60, 2025-07-28 --SJRWMD RFQ 41325]
Page 60, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 61, 2025-07-28 --SJRWMD RFQ 41325]
Page 61, 2025-07-28 –SJRWMD RFQ 41325
PDF

[Page 62, 2025-07-28 --SJRWMD RFQ 41325]
Page 62, 2025-07-28 –SJRWMD RFQ 41325
PDF

2 thoughts on “Water First North Florida wetland locations: unknown –SRWMD 2025-12-17

  1. Pingback: SRWMD & SJRWMD aquifer recharge project update @ SRWMD 2025-07-08 | WWALS Watershed Coalition (WWALS) is Suwannee RIVERKEEPER®

  2. Pingback: Drought Workshop Presentation –SRWMD 2025-12-09 | WWALS Watershed Coalition (WWALS) is Suwannee RIVERKEEPER®

Leave a Reply

Your email address will not be published. Required fields are marked *