Four more Valdosta sewage spills 2023-12-17

Update 2024-02-22: Some Knights Creek plans in Valdosta Boone Drive and Knob Hill small sewage spills 2024-02-20.

Update 2024-01-31: Spill from Chemours Trail Ridge South TiO2 mine SE of Starke, FL 2024-01-30.

Four small Valdosta sewage spills appeared in the January 26, 2024 GA-EPD Sewage Spills Report, all listed as happening December 17, 2023, and as “Did not enter State waters”.

[Four small Valdosta sewage spills 2023-12-17]
Four small Valdosta sewage spills 2023-12-17

However, Valdosta Acting Utilities Director Jason Barnes confirms that these spills did happen. Which you can see for yourself in the pictures I took on January 23 of the Mile Street spill locations.

The most unusual part of these spill reports is that bit for “WATERWAY IMPACTED”: “Did not enter State waters”. That means these spills were stopped and contained before they could reach Knights Creek or Cherry Creek. Which is impressive considering that Sunday, December 17, 2024, saw more than an inch of rain at every gauge we follow, after more than half an inch the previous day. (See below for one reservation about one of these spills.)

Nobody is going to be happy until the number of Valdosta sewage spills is zero. And WWALS continues watching closely.

However, watching also includes complimenting Valdosta Utilities when things go right. So, congratulations, Valdosta Utilities, for catching these spills before they did any damage.

Curiously, these spills did not appear in the next day’s Sewage Spills Report, or in any later days. Considering recent typos in those GA-EPD Sewage Spills Reports, I’m assuming those later omissions are due to EPD’s problems with lack of staffing and funding.

Let’s look at each of these spills. Continue reading

End date and waterway affected of Valdosta 425,000 gallon sewage spill 2023-12-11

Update 2024-01-28: Valdosta Knights Creek water quality test results in Four more Valdosta sewage spills 2023-12-17.

Update 2023-12-22: Bad water quality, Withlacoochee and Santa Fe Rivers 2023-12-21.

The Valdosta written report about its December 11, 2023, 425,000-gallon sewage spill, received in response to a WWALS open records request to GA-EPD, contains some information that was not in the Valdosta press release. Including a bit more about corrective action than was in the reports of the two previous spills.

Plus Valdosta has started posting water quality test results upstream and down from the spill location.

More about that and the spill location below.

[Valdosta Report, Map, GA-EPD Sewage Spills Report, Valdosta Water Quality Results]
Valdosta Report, Map, GA-EPD Sewage Spills Report, Valdosta Water Quality Results

Here’s the spill report. As you can see, it has both the start and stop dates and times of the spill: start 9:30 AM December 11, end 6 PM December 14. GA-EPD also returned the Valdosta Utilities cover letter of the report, which was sent Friday, December 15, 2023 2:20 PM. Which confirms what Valdosta Utilities Acting Director Jason Barnes told me on the phone: the report went in (and the Valdosta press release went out) after the spill stopped.

The affected waterway is identified, as “Knights Creek/Mud Creek”, and the creek is also named at the top of the report:
MAJOR SPILL REPORT TO EPD Knights Creek Sanitary Sewer Spill.”

As you know, Knights Creek flows into Mud Swamp Creek, then the Alapahoochee River, the Alapaha River in Florida, and the Suwannee River, on the way to the Gulf of Mexico.

The report gives the cause as equipment failure, not blamed on the contractor:
CAUSE OF MAJOR SPILL: Bypass pump failure and Hydraulic Overload”

And there is more about what the city did and what it plans to do to prevent such spills. Continue reading