Tag Archives: IC-SE-01-2026

Irwinville Data Center Withdrawn by Applicant, Irwin County Commission 2026-03-02

Here’s a reason to stay until the end of a County Commission meeting.

A proposed data center ordinance was read at the March 2, 2026, Irwin County Commission meeting, according to correspondence between the former data center applicant’s attorney and the Irwin County Attorney.

It was not on the agenda. I’m guessing they read it under

13. NEW BUSINESS

a. APPROVE APPLICATION FOR A SPECIAL EXCEPTION TO ZONING FOR DATA CENTER

Tomorrow in Ocilla there is a a Public Hearing about Datacenter Ordinance –Irwin County Board of Commissioners 2026-03-17.

https://wwals.net/?p=69663

[Irwinville Data Center, Withdrawn by Applicant 2026-03-02, Irwin County Commission, and Developments of Regional Impact (DRI)]
Irwinville Data Center, Withdrawn by Applicant 2026-03-02, Irwin County Commission, and Developments of Regional Impact (DRI)

I got the attorney correspondence by asking in an open records request for the applicant withdrawal letter that staff read at the Public Hearing on March 2.

First, that withdrawal letter.

Then a document on Developments of Regional Impact (DRI).

Then a couple of maps labeled as Concept Site Plan with the name for the project as Ocilla DC.

Finally, there are images of the rest of the document the County Attorney sent in response to a WWALS open records request. The entire PDF document he sent is on the WWALS website. Continue reading

Datacenter: recommended approval –Irwin County Planning Commission 2026-02-26

Update 2026-03-02: Datacenter Special Exception Public Hearing @ Irwin County Commission 2026-03-02.

All four Planning Commissioners present voted to recommend approval of the proposed Special Exception for the Data Center near Irwinville, last Thursday, February 26, 2026.

[Datacenter: recommended approval, Irwin County Planning Commission, After many speakers, most against 2026-02-26]
Datacenter: recommended approval, Irwin County Planning Commission, After many speakers, most against 2026-02-26

The next stop is the Irwin County Commission, this Monday, March 2, 2026, at 5:45 PM, in the same location, the Irwin County Courthouse, 301 South Irwin Avenue, Ocilla, Ga. 31774.

After numerous people spoke against and a few for that item, IC-SE-01-2026, two of the members of the Ocilla-Irwin County Planning Advisory Commission spoke at length about what they had been told or read or saw on a visit to another datacenter, as why they were for it, plus the promise of $20 million a year in tax revenue.

None of that was in the extremely thin board packet. So thin that their staff, Jessica Harris, Irwin County Interim Chief Appraiser, said at the beginning of that item that staff had no recommendation for or against because there was not enough information to go on.

The other two Planning Commissioners said they were for tabling the item due to lack of information.

However, one of the two for the project, Chairman Alan Smith, moved for approval. The other one, Vice Chair Tara Smith, seconded. And the remaining two, Arlinda Murrell and Ms. Walker, reluctantly also raised their hands.

Questions not answered with any documentation continue to include who is the datacenter customer (Google?), where are the specifications for the closed loop cooling water system, and what would those 200-300 high-paying local permanent jobs be doing, that were advertised in the slides for Irwin Forward Tech Park.

The proposed location is on Ponderosa Drive, Irwinville, Georgia 31783, quite near the Alapaha River.

Below are links to each WWALS video of each speaker or topic, with a few notes by John S. Quarterman, followed by a WWALS video playlist.

Most speakers were against the special exception, except for the few noted as for or as part of or attorney for the applicant.

Apologies for any incorrect names. And Continue reading