The Irwinville datacenter is back and bigger, this time called Project Arrowhead for 4,220,000 SF, Approximately 1066 acres.
The Irwin County government on April 10, 2026, submitted an application as a Development of Regional Impact (DRI) to the Georgia Department of Community Affairs (GA-DCA).
The new five-tract campus includes the old one and extends farther east, across Ponderosa Drive to Pinetta Road.
For more about datacenters, see:
https://wwals.net/issues/datacenters/#irwinco
Project Arrowhead Datacenter DRI application 2026-04-10, Irwin County, GA, near Alapaha River
According to the Initial Form, the location is “31°35&min;57.00&sec;N, 83°22&min;2.79&sec;W. Parcel numbers 0018 0007, 0026 0001, 0026 0003, 0026 00040AA, and a p”
That’s right, the last parcel is truncated. But it must be the one where the latlong leads, which is parcel 0035 0009, owned by Marcus D Fletcher Trust, trustee Angie F Bryan, 641.67 acres. That east parcel conveniently has a power line on it.
It’s connected to the former land west of Ponderosa Drive through parcel 0026 0040AA, owned by Sirrom Farms, LLC, 120.19 acres. Continue reading