Six hours and no decision @ Alachua Planning Commission 2026-01-13

The City of Alachua Planning Commissioners seemed inclined to approve the Special Exception Permit for the Tara April detention ponds and trails next to I-75.

But after the applicant’s case was countered by the National Speleological Society (NSS) and others, the Commissioners seemed ready to deny.

However, at midnight the court recorder had to leave, so they had to adjourn until Tuesday, April 20, 2026, at 6 PM, also at Alachua City Hall, 15100 NW 142 Terrace, Alachua, FL 32615.

Get there early. It was standing room only this Tuesday, with some people outside the doors.

[Six hours and no decision, @ Alachua Planning Commission 2026-01-13, They meet again about Tara April, and Mill Creek Sink, 6 PM 2026-01-20]
Six hours and no decision, @ Alachua Planning Commission 2026-01-13, They meet again about Tara April, and Mill Creek Sink, 6 PM 2026-01-20

You can see the relevant parts of the meeting (minus the other two items on the agenda) in this video by Richie Denmark for NSS:

https://youtu.be/g2yNv9MtRBY?si=dtbvAtyaEnXwmvVw

That video does not include the images projected by the various speakers. But I took stills of many of them, which you can see below.

The video starts with me photographing the Tara April Master Plan. You can see my photographs below. Continue reading