Tag Archives: Guess Road

Report: Conditions wanted on Morven Solar by Brooks County Planning Commission 2023-01-20

Update 2023-02-06: Videos: Morven Solar at Brooks County Planning Commission 2023-01-19.

In front of a standing-room-only audience, and after long hesitation, the Brooks County Planning Commission voted 3-1 to recommend Conditional Approval for the Morven Solar project, pending “A Valid Road use Agreement put in-place” and “Erosion Measures provided and Filtration Plants in the Retention Ponds”.

Here is the report sent from the Planning Commission to the County Commission for its decision on February 6th. The report has some puzzling omissions.

[Meeting 2023-01-19, Recommendation 2023-01-20]
Meeting 2023-01-19, Recommendation 2023-01-20

Staff still recommends denial, and the included Staff Analysis is the same as provided before the Planning Commission meeting. Continue reading

Pictures: sites of Morven Solar 2023-01-18

Update 2023-01-21: Report: Conditions wanted on Morven Solar by Brooks County Planning Commission 2023-01-20.

To help visualize what Morven Solar is proposing tonight at the Brooks County Planning Commission, yesterday I took a few pictures.

They include the pecan trees to be cleared for the project that county (SGRC) staff pointed out were not included in the tree survey, as well as the planted pines that were included, and some natural trees that are to be kept as a buffer.

Most of the project is on current center pivot irrigation cotton fields, with the agricultural pesticides that implies.

Which raises one of several questions: will the solar project also use pesticides, or will it adopt another method, such as sheep or goats?

[Parts of the Morven Solar project sites 2023-01-18]
Parts of the Morven Solar project sites 2023-01-18

This is the layout of the project: Continue reading

Agenda: One item, Morven Solar @ Brooks County Planning Commission 2023-01-19

Update 2023-01-18: Pictures: sites of Morven Solar 2023-01-18.

It may be a long meeting even with only one item, since Morven Solar seems to be contentious.

[Aerial Map of Morven Solar and Agenda, Brooks County Planning Commission 2023-01-19]
Aerial Map of Morven Solar and Agenda, Brooks County Planning Commission 2023-01-19

Here is the agenda, received in response to a WWALS open records request from Brooks County Zoning and Code Enforcement Agent Melissa Smith. Continue reading

Morven Solar rezoning proposed around Slaughter Creek, Little River @ Brooks County Planning Commission 2023-01-19

Update 2023-01-18: Agenda: One item, Morven Solar @ Brooks County Planning Commission 2023-01-19.

A large solar project, in agricultural fields and pecan groves scattered around wetlands, will be heard by the Brooks County Planning Commission at 5:30 PM this Thursday, January 19, 2023, at 610 S Highland Road, Quitman, GA 31643.

[Morven Solar, Slaughter Creek, Withlacoochee River]
Morven Solar, Slaughter Creek, Withlacoochee River

Staff’s recommendation:

Due to the staff’s concern of the amount of “prime farmland”, the quantity of jurisdictional wetlands, the threatened and candidate species potential impacts, and the amount of access roads because the parcels are not contiguous (especially Peach Road — dirt), the Staff recommends DENIAL of the applicant’s proposed use as a Large-Scale Solar Energy System.

WWALS is generally in favor of solar power, but this project raises serious doubts, most of which are expressed in the Staff Analysis.

The final decision will be made by the Brooks County Commission, 5:00 PM, Monday, February 6, 2023, also at 610 S Highland Road, Quitman, GA 31643.

The project is between Morven and Hahira, straddling Slaughter Creek, upstream from the Little River. Continue reading