Does this look anywhere near completion to you?
Yet on March 26, 2020, Sabal Trail asked FERC to extend the May 1st deadline for its Phase II construction of the Dunnellon and Albany Compressor Stations because of the virus pandemic, after FERC already extended way past the original February 2, 2018, deadline for completion of all phases.
FERC surprisingly did not immediately rubberstamp that request, instead opening a comment period until April 13, 2020. WWALS today filed a Motion to Intervene in that comment process on that request.
Your organization, if it was a party to the underlying Sabal Trail proceeding in FERC Docket CP15-17, can also move to intervene.
https://ferc.gov/docs-filing/efiling.asp
Anyone can comment, without needing to intervene:
https://ferc.gov/docs-filing/ecomment.asp
WWALS Motion to Intervene
See also the PDF filed with FERC as Accession Number 20200406-5070 today, April 6, 2020. Continue reading