Review and comment: DRI for Project Arrowhead Datacenter, Irwin County, GA 2026-04-24

Everyone has two weeks, until Monday, May 11, 2026, to review and comment on the Development of Regional Importance (DRI) application by Project Arrowhead to build a huge datacenter in Irwin County, Georgia, near Irwinville and the Alapaha River.

The attachments SGRC sent are on the WWALS website, with images of each page below.

https://wwals.net/pictures/2026-04-24-dri-irwin-county-project-arrowhead

I see nothing from the applicant that WWALS hasn’t previously posted, such as when the DRI application appeared on April 10.

The Southern Georgia Regional Commission (SGRC) has helpfully annotated the Kimley-Horn site maps we saw back in March, and added other useful maps.

Plus SGRC points out the most significant part of the Data Center Ordinance the Irwin County Commission passed on April 6: the table permitting a Data Center as a Special Exception (SE) allowable use in the Agriculture (A-U), Heavy Industrial (H-I), and the Adult Commercial (C-A). I’m not sure that ordinance added SE for A-U, but it certainly called it out.

For much about what we do not know, such as who the real applicant is, or what closed loop cooling means in this case, see Who is Project Arrowhead in Irwin County, GA? –Vesper 2026-04-16.

https://wwals.net/?p=70067

For much more about Datacenters, see:

https://wwals.net/issues/datacenters

[Review and comment: DRI for Project Arrowhead Datacenter, Irwin County, GA, Comment to SGRC by May 11, 2026]
Review and comment: DRI for Project Arrowhead Datacenter, Irwin County, GA, Comment to SGRC by May 11, 2026

Received by email Friday, April 24, 2026, at 7:32 PM:

Greetings All:

You are receiving this email because you are affiliated with a city, county, state government, or other concerned agency that could be affected by a proposed data center development for Irwin County, Georgia. The size and scale of a proposed data center development in Irwin County, Georgia has either met or exceeded the threshold for a required Development of Regional Impact (DRI) review as mandated by the State of Georgia. By virtue of this email, you now have the opportunity to review and comment on the proposed development prior to it moving forward. Please assess how it may affect your jurisdiction and place those comments on the form provided.

Attached to this email is a packet of information that concerns the Irwin County DRI # 4689 which has been formally submitted to the Georgia Department of Community Affairs DRI site. Please review the packet and, if you feel so inclined, please fill out the comment form and return it to me with your comments no later than the close of business on Monday May 11, 2026.

Please feel free to contact me with any questions that you may have concerning the packet of materials that you have received.

To view the DRI #4689, Project Arrowhead Part 1 and Part 2 application on the Georgia Department of Community Affairs website, please use the following link:
https://apps.dca.ga.gov/DRI/default.aspx

Thank you,
James A. Horton, MHP
Planning Director
SGRC
1937 Carlton Adams Drive
Valdosta, GA 31601
(229) 333-5277

 -jsq, John S. Quarterman, Suwannee RIVERKEEPER®

You can help with clean, swimmable, fishable, drinkable, water in the 10,000-square-mile Suwannee River Basin in Florida and Georgia by becoming a WWALS member today!
https://wwals.net/donations/

[DRI Comment Form, Blank, Fillable, 2026-04-24 --SGRC]
DRI Comment Form, Blank, Fillable, 2026-04-24 –SGRC
PDF

NDRI

[NOTICE OF DEVELOPMENT OF REGIONAL IMPACT, Project Arrowhead Data Center Irwin Co. DRI 2026-04-24 --SGRC]
NOTICE OF DEVELOPMENT OF REGIONAL IMPACT, Project Arrowhead Data Center Irwin Co. DRI 2026-04-24 –SGRC
PDF

[DRI Report for Comment Purposes]
DRI Report for Comment Purposes
PDF

[Utility Needs and Arrangements for Project Arowhead]
Utility Needs and Arrangements for Project Arowhead
PDF

DRIIIF

[DRI Initial Information Form]
DRI Initial Information Form
PDF

[Page 5]
Page 5
PDF

[Page 6]
Page 6
PDF

DRIIFP2

[DRI Information Form Part 2]
DRI Information Form Part 2
PDF

[Economic Development; Water Supply]
Economic Development; Water Supply
PDF

[Wastewater Disposal; Land Transportation]
Wastewater Disposal; Land Transportation
PDF

[Solid Waste Disposal; Energy Supply]
Solid Waste Disposal; Energy Supply
PDF

[Georgia Power is in the process of completing an energy study for the project.]
Georgia Power is in the process of completing an energy study for the project.
PDF

[Stormwater Management; Environmental Quality]
Stormwater Management; Environmental Quality
PDF

KH-2025-02-01

[Overall Concept Site Plan, Ocilla DC, City of Ocilla, Irwin County, GA, 2025-02-01 --Kimley Horn, Mobile, AL]
Overall Concept Site Plan, Ocilla DC, City of Ocilla, Irwin County, GA, 2025-02-01 –Kimley Horn, Mobile, AL
PDF

[Concept Site Plan, Ocilla DC, City of Ocilla, Irwin County, GA, 2025-02-01 --Kimley Horn, Mobile, AL]
Concept Site Plan, Ocilla DC, City of Ocilla, Irwin County, GA, 2025-02-01 –Kimley Horn, Mobile, AL
PDF

ICCP-2024-03-04

[Irwin County Character Area Map from the 2024-2029 Irwin County and Ocilla Comprehensive Plan adopted 2024-03-04. The character area for Project Arrowhead is currently Agricultural/Forestry Character Area. --SGRC]
Irwin County Character Area Map from the 2024-2029 Irwin County and Ocilla Comprehensive Plan adopted 2024-03-04. The character area for Project Arrowhead is currently Agricultural/Forestry Character Area. –SGRC
PDF

[Agricultural/Forestry Character Area, 2024-03-04 Irwin County Comprehensive Plan]
Agricultural/Forestry Character Area, 2024-03-04 Irwin County Comprehensive Plan
PDF

[Zoning Map, Irwin County, 2024-03-04 Project Arrowhead site in Agricultural Use area (A-U). --SGRC]
Zoning Map, Irwin County, 2024-03-04 Project Arrowhead site in Agricultural Use area (A-U). –SGRC
PDF

[Excerpt from the Zoning Ordinance for Irwin County, Georgia, 2026-04-06 showing a Data Center as a Special Exception (SE) allowable use in the Agriculture (A-U), Heavy Industrial (H-I), and the Adult Commercial (C-A).]
Excerpt from the Zoning Ordinance for Irwin County, Georgia, 2026-04-06 showing a Data Center as a Special Exception (SE) allowable use in the Agriculture (A-U), Heavy Industrial (H-I), and the Adult Commercial (C-A).
PDF

AMaps-2026-04-24

[Annotated Concept Site Plan, 2026-04-24 --Kimley-Horn annotated by SGRC]
Annotated Concept Site Plan, 2026-04-24 –Kimley-Horn annotated by SGRC
PDF

[Annotated Overall Concept Site Plan, 2026-04-24 --Kimley-Horn annotated by SGRC]
Annotated Overall Concept Site Plan, 2026-04-24 –Kimley-Horn annotated by SGRC
PDF

[Irwin County, Georgia Wetland Mapper, 2026-04-24 https://fwsprimary.wim.usgs.gov/wetlands/apps/wetlands/mapper]
Irwin County, Georgia Wetland Mapper, 2026-04-24 https://fwsprimary.wim.usgs.gov/wetlands/apps/wetlands/mapper
PDF

[Project Arrowhead site outlined in orange color on the wetlands map for the site area. 2026-04-24 https://fwsprimary.wim.usgs.gov/wetlands/apps/wetlands-mapper/]
Project Arrowhead site outlined in orange color on the wetlands map for the site area. 2026-04-24 https://fwsprimary.wim.usgs.gov/wetlands/apps/wetlands-mapper/
PDF

BF

[DRI Comment Form, Blank, Fillable, 2026-04-24 --SGRC]
DRI Comment Form, Blank, Fillable, 2026-04-24 –SGRC
PDF