Many people were disappointed in the informational tables about Water First North Florida (WFNF), the plan to pipe treated wastewater from Jacksonville into the Suwannee River Basin.
For much more about WFNF, see
Pictures: SRWMD WFNF, Open House, UF IFAS, Live Oak, FL, Thursday, March 19, 2026
WCTV’s subhead is incorrect about the Community Open House by SRWMD, 6-8 PM, Thursday, March 19, 2026, at UF-IFAS in Live Oak, Florida:
“This project wouldn’t happen until 2039”
According to their own schedule, many parts of WFNF are already happening, such as the three-year consultant wetland pilot study and siting study funded by SJRWMD in November 2025. The first pipes would start going in in 2028: “Transmission Mains to Wetland.” Pipes to recharge facilities, i.e., those in the Suwannee Basin, would start going in in 2032. It’s only the final complete turn on of the entire project that might not start until 2039. Continue reading