Come hear about the $60 million in wastewater fixes Valdosta just finished, what remains to be done, and what they’re doing about flood prevention for the entire Suwannee River Basin in Georgia and Florida. You can ask questions in this first of a new WWALS Quarterly Speaker Series, and the people organizing this work will be there to answer:

  • Henry Hicks, Utilities Director, about wastewater
  • Emily Davenport, Assistant Director of Engineering, about flooding, and
  • Tim Carroll, Valdosta City Council, about solar power for utilities.

When: 6PM Thursday October 27th

Where: Valdosta City Hall Annex
Multipurpose Room
300 N Lee St.
Valdosta, GA 31601 Continue reading

Details on Valdosta overflows last weekend 2016-04-04

Force main and the new WWTP on line by May!

More extensive overflows than usual last weekend, and now more extensive information about them, in the update Tim Carroll promised, on the City of Valdosta website as City System Impacted by Severe Storms and Regional Watershed. It even starts with schedule details, which say they’re ahead of the schedule I previously posted. This report’s table of overflows has start and stop times and amounts, with the Creeks affected.

It still doesn’t say which river basin they go into. Knights Creek flows into Mud Creek, which goes into the Alapahoochee, Alapaha, and Suwannee Rivers. All the others end up in the Withlacoochee and the Suwannee Rivers. And there are still some unanswered questions. But getting the force main and the new WWTP on line by May is a very good development.

The City of Valdosta is ahead of schedule and plans to bring online nearly $60 million in wastewater system improvements next month. The $35 million Force Main project and the $23 million new Withlacoochee Wastewater Treatment Plant (WWTP) are both ahead of schedule, and bringing them both online cannot come a day too soon for the city. 

“We are pleased to be in the final stages of construction on both projects. Testing is underway now with full startup expected in late May,” according to Director of Utilities Henry Hicks. “We are also pleased that these projects and other awarded sewer collection system improvement projects underway will resolve all the areas of the city impacted by reoccurring overflows that often follow heavy rains and regional flooding.”

Continue reading

More Valdosta wastewater spills over the weekend; stay tuned 2016-04-04

Update 2016-04-05: Here are the details, and force main and new WWTP on line by May.

Valdosta spilled more wastewater over the weekend, according to Valdosta City Council Tim Carroll, who called just now. The Withlacoochee River is out of its banks, actually up on the property containing the Withlacoochee Wastewater Treatment Plant (WWTP), but “according to the experts” not going to threaten the plant. “But lines are underwater”.

Water is not even close to the new WWTP currently under construction, according to Carroll. And the new force main project should deal with much of the manhole overflow problem on the west side of Valdosta in the Withlacoochee basin, for example into Sugar Creek.

On the east and southeast, in the Alapaha basin, Continue reading