Datacenters meeting, Lowndes County, GA 2026-02-17

Update 2026-02-24: Datacenter electricity SB 34 in GA Senate Committee 2026-02-24.

As I said at the end, we saw unprecedented transparency from the property owner and Georgia Power, at the Lowndes County meeting about datacenters, February 17, 2026, at Valdosta State University.

We still need much more due diligence and we need a datacenter ordinance by Lowndes County.

[Unprecedented transparency, Need much more due diligence, Datacenter meeting, VSU, Lowndes County, GA 2026-02-17]
Unprecedented transparency, Need much more due diligence, Datacenter meeting, VSU, Lowndes County, GA 2026-02-17

I thank Pope Langdale for revealing that the datacenter would be by DC BLOX, and that their CEO had promised him closed loop cooling with minimal water from county utilities and a large number of high-paying jobs.

However, that CEO’s job is to be chief salesman for his product. Where are the specifications of this closed loop system? Where are some locations of DC BLOX datacenters we can all examine to see how they actually work? And ask their neighbors what they think? The DC BLOX website says they have 17 locations, and has a map with city or county names, but no further information.

Please listen to the experts on the panel and the people in the room, especially the students, who said they have not been able to find any datacenter neighbors who have had a positive experience.

I understand Joe Brownlee of Georgia Power’s wish to provide jobs and tax revenue. But, as I discussed with him after the meeting, it’s not good to get too dependent on a business that may vanish soon. Plus he is well aware that I and WWALS differ with he and Georgia Power about natural gas pipelines and power plants, more of which are now proposed to power these datacenters in Georgia.

We’ve all heard promises of many high-paying jobs before. The Sabal Trail pipeline promised that. Which turned out to be construction jobs outsourced to contractors from Texas and Oklahoma.

To the person who demanded Pope Langdale get the Lowndes County Commission to pass a datacenter ordinance: be careful what you wish for. You do not actually want local rich people completely controling local governments. You all need to be getting an ordinance passed.

Meanwhile near Irwinville, a special exception for a datacenter is on the agenda for the Ocilla/Irwin County Planning Commission this Thursday, February 26, 2026.

https://wwals.net/?p=69394

Amy Sharma’s Science for Georgia presentation slides are on the WWALS website, in PowerPoint and PDF, and on google drive.

The model datacenter ordinances by Science for Georgia are also on the WWALS website, or follow the QR code: Continue reading

Videos: Vote on wood pellet farm –Adel City Council 2020-09-21

The Adel, Georgia, City Council passed the two ordinances for the wood pellet plant with no discussion, yet with some votes against, and protestors outside and inside, on September 21, 2020. There are still things you can do to stop this polluting project that would export our trees from throughout the Suwannee River Basin and beyond, to Europe to burn, producing yet more CO2.

[Protesters outside and in, and the Adel City Council split vote for the wood pellet plant]
Protesters outside and in, and the Adel City Council split vote for the wood pellet plant

Below are links to each LAKE video of those agenda items, with a few notes.

See also Vicki Weeks, Dogwood Alliance, 16 October 2020, Industrial Logging and the Wood Pellet Industry Hurt Us All.

And Dogwood Alliance’s petition to call on Georgia leaders to protect our forests.
https://www.dogwoodalliance.org/actions/stop-the-destruction-of-georgia-forests/

You can also ask GA-EPD to reject the air permit application. Probably more on that later.

For background, see: Continue reading

Wood pellet plant: speakers and documents @ Adel City Council 2020-09-08

Update 2020-09-11: fixed document and map links and added form for comments.

The Adel City Council had no questions after their Public Hearing on annexation and rezoning for a wood pellet plant, Tuesday, September 9, 2020, after thirty minutes of speakers for and against.

That was just the first reading. The second reading will be 5:30 PM, Monday, September 21, 2020, at Adel City Hall.

[Maps and speakers, wood pellet plant, Adel City Council 2020-09-08]
Maps and speakers, wood pellet plant, Adel City Council 2020-09-08

After the meeting I asked the City Manager, the City Clerk, and a couple of City Council members what maps and plans they had looked at. They all said they hadn’t seen any, and maybe I should talk to Economic Development. So I asked her, and she didn’t seem to indicate she’d seen any.

Yet there are maps and plans in the air permit application to GA-EPD, and others reviewed by the Planning Commission, which, as the City Manager pointed out during the meeting, issued a Public Notice of its public hearing on July 6, 2020. I don’t know why these state and county agencies have not published these documents, nor why the City of Adel has not. But those are public documents, so here they are (see Air Quality Permit maps and Planning Commission maps).

Below are videos by Lowndes Area Knowledge Exchange (LAKE) of the pellet plant part of the Adel City Council meeting. See also the agenda and the WWALS letter to the Adel City Council. See also some helpful documents by the Dogwood Alliance

And this handy Dogwood Alliance form to send a comment to the Adel City Counci l.

By the way, this kind of work does take time and effort, so feel free to contribute to WWALS. . Continue reading