Videos: Datacenter Special Exception approved at Special Called Meeting of Irwin County BOCC 2026-05-20

The Irwin County Commissioners approved almost everything unanimously, including the Special Exception for a datacenter.

[Videos: Datacenter Special Exception Approved at Special Called Meeting of Irwin County BOCC 2026-05-20]
Videos: Datacenter Special Exception Approved at Special Called Meeting of Irwin County BOCC 2026-05-20

The only exception was 6. ACCEPT PHASE II OF THE COURTHOUSE ROOF BID PROJECT, which they tabled.

On the datacenter special exception, several Commissioners did express specific concerns. But they seemed to be relying largely on hearsay, such as by the Commissioners who had visited some datacenters, which “wasn’t really rushed,” yet “We were rushing to see everything we could see. And we didn’t get all the questions like that answered.” Continue reading

Signed Irwin County Datacenter Ordinance 2026-04-06

It looks like the Irwin County Commission added a few things about water, power, and enforcement to their draft datacenter ordinance before they passed it.

The final version, received today in response to a WWALS open records request, is on the WWALS website.

For comparison, a copy of the original draft is here:

https://wwals.net/?p=69663

Do you see any other differences?

For more about datacenters, see:

https://wwals.net/issues/datacenters

[Signed Irwin County Datacenter Ordinance 2026-04-06, Changes to Water, Energy, Enforcement]
Signed Irwin County Datacenter Ordinance 2026-04-06, Changes to Water, Energy, Enforcement

Subclause (3) is new on page 4:

(d) Water Usage Standards.

(1) Only closed-loop cooling systems are permitted in Irwin County.

(2) There shall be no discharge of cooling water into public sewers or ground without treatment.

(3) Before a certificate of occupancy is provided, all data centers shall submit a hydrogeologic study conducted by an independent third-party engineering firm showing estimated annual water usage. Such report should compare estimated water usage to the prior owner/user of the subject property or of that of similar surrounding areas.

Also on page 4, this subclause (1) is new: Continue reading

Videos: Public Hearing about Datacenter Ordinance –Irwin County Board of Commissioners 2026-03-17

Update 2026-04-20 Signed Irwin County Datacenter Ordinance 2026-04-06.

Here are WWALS videos of the first Irwin County Commission Public Hearing about a Data Center Ordinance, on March 17, 2026.

The next Public Hearing will be March 30, 2026 at 5:45p.m in the Irwin County Courthouse, located at 301 South Irwin Avenue, Ocilla, Georgia.

The third and last Public Hearing will be April 6, 2026, before the Irwin County Commission meeting, presumably also at 5:45 PM and at the Courthouse.

[Videos: Public Hearing about Datacenter Ordinance --Irwin County BOCC, 2026-03-17]
Videos: Public Hearing about Datacenter Ordinance –Irwin County BOCC, 2026-03-17

Among the many good points brought up by citizens at the March 17 Public Hearing were the need for much more due diligence, tuning the ordinance to prevent specific harms, enforcement of the ordinance, as well as specific concerns of cost of wells, water levels, water quality, vegetative buffers, waste disposal, air quality, noise levels, wildlife, electric power, property values, agriculture, the Alapaha River, and limits on the size of any datacenters.

Despite a persistent rumor, the Irwin County Commission definitely did not vote on the previous datacenter application, because the applicant withdrew the application, so there was nothing to vote on.