Videos: Naylor Boat Ramp should be finished in two weeks @ LCC 2019-06-10

The Naylor Boat Ramp on the Alapaha River should be finished in about two weeks, said Lowndes County Manager Joe Pritchard in yesterday morning’s Lowndes County Commission Work Session. Below are videos of that meeting by Lowndes Area Knowledge Exchange (LAKE).

Slab curing at Naylor Boat Ramp 2019-05-21

The concrete was curing Tuesday, May 21, 2019, that was poured after May 8, following the bed built by April 30. With representative human Many people want to know: when will Lowndes County slide this slab down into the river? I am not Lowndes County Project Manager Chad McLeod, but my guess is

Naylor Boat Ramp Park is not Lola VPA or WMA 2019-05-19

If you’re down at the beach on the Alapaha River, just upstream from US 84, in the new Lowndes County Naylor Boat Ramp Park, and a game warden should happen to say you need a WMA pass, please tell him you’re in a public park owned by Lowndes County, and if there’s any doubt about […]

Naylor Boat Ramp, Water Trails, and Paddle Georgia: WWALS to Lowndes County Commission 2019-05-13

Thanks and invitations from WWALS to the Lowndes County Commission, delivered in a letter via email and on paper Monday morning and in Citizens Wishing To Be Heard Tuesday evening. I thanked Lowndes County Utilities Director Steve Stalvey and the Commissioners for fixing a force main before it breaks. County Engineer Mike Fletcher and Project […]

Naylor Boat Ramp framed 2019-05-08

Frame and concrete wire. Frame Lowndes County Project Manager Chad McLeod says they will probably pour the concrete Saturday. Then 10 to 14 days to set before pushing into the Alapaha River for Naylor Boat Ramp.

Naylor Boat Ramp poured 2019-04-30

Update 2019-05-08: Now with framing and concrete wire. Update 2019-05-06: OK, as April Huntley pointed out after went out there over the weekend, the concrete is not poured yet: what’s out there is the bed on which to put the concrete. I called Lowndes County Project Manager Chad McLeod, who said that’s right. Today the […]

Naylor Boat Ramp status @ LCC 2018-09-10

The Naylor Boat Ramp should finally be complete within a few weeks, said Project Manager Chad McLeod at Monday’s Lowndes County Commission Work Session. It will be interesting to see what paddlers report back from that site after yesterday’s paddle starting there as part of the Alapaha Quest to paddle in segments the entire Alapaha […]

Alapaha Quest, Naylor Boat Ramp @ US 84, 2018-09-15

Update 2019-09-14: We’ve moved downstream, to put in at Naylor Boat Ramp and take out at Mayday Landing. This section does have some rough rocky spots with rapids for a short distance. The takeout at Mayday is a little difficult due to soft sand to climb up to the parking area. Bring plenty of water […]

Naylor Boat Ramp 2018-05-16

The actual boat ramp hasn’t been built yet. Lowndes County Engineering says they’re waiting for the Alapaha River level to go down again. Right now it’s a straight drop. Straight to the drop, 2018:05:16 11:20:49,, Boat Ramp Entrance 30.9257700, -83.0394900 Once the county finishes this project, they will hand over to the Valdosta-Lowndes County Parks […]

Hotchkiss Road Landing, Old State Road, and Naylor Boat Ramp

Common question: isn’t Hotchkiss closed? Answer: the old Hotchkiss Landing in Lowndes County is closed, private, and don’t go there! But Hotchkiss Road Landing in Lanier County is open as always, do go there to get to the Alapaha River. And there’s a new park at US 84, with a Naylor Boat Ramp being built […]