Flood Inundation Mapper (FIM) 2019-10-21

Valdosta and Lowndes County spent some money for LiDAR to map flooding extents at various Withlacoochee River water levels. The result is in the USGS Flood Inundation Mapper.

The map starts just below the Skipper Bridge Gauge on the new Skipper Bridge, down to the GA 133 Withlacoochee River Bridge. Too bad they didn’t go about a thousand river feet farther down to the Little River Confluence.

Here are some screenshots at various levels.

[10.7feet]
10.7feet

Click on any small picture to see a larger one. Continue reading

Videos, Valdosta Wastewater and Flood Prevention 2016-10-27

The crowd was very attentive to every word about wastewater and flood prevention, with officials from the City of Valdosta presenting in the first of a new quarterly WWALS speaker series. If you didn’t come, you can see and hear in these videos Henry Hicks about wastewater, Emily Davenport about flood prevention, Tim Carroll about solar power, and Sementha Mathews about how to get more information from Valdosta. WWALS Treasurer and acting Executive Director Gretchen Quarterman opened and closed the meeting.

Each talk had many small but important stories, so we will probably blog more posts about those. Meanwhile, here are the videos: see for yourself! Continue reading

Valdosta wastewater and flood prevention public meeting by WWALS 2016-10-27

New WWTP, 30.8327808, -83.3283234 Update 2016-10-23: Seen from the air.

Update 2016-10-19: PDF flyer.

Come hear about the $60 million in wastewater fixes Valdosta just finished, what remains to be done, and what they’re doing about flood prevention for the entire Suwannee River Basin in Georgia and Florida. You can ask questions in this first of a new WWALS Quarterly Speaker Series, and the people organizing this work will be there to answer:

  • Henry Hicks, Utilities Director, about wastewater
  • Emily Davenport, Assistant Director of Engineering, about flooding, and
  • Tim Carroll, Valdosta City Council, about solar power for utilities.

When: 6PM Thursday October 27th

Where: Valdosta City Hall Annex
Multipurpose Room
300 N Lee St.
Valdosta, GA 31601 Continue reading

Lowndes County to match Valdosta funding for LiDAR flood mapping? 2016-07-11

Valdosta already had an airplane fly over Lowndes County and collect Light Detection and Ranging (LiDAR) data for flood mapping. Will Lowndes County step up and match Valdosta on this project that affects everybody in the county (and downstream into Florida)? Valdosta started this LiDAR project in March 2015, and Valdosta fronted the entire cost to get it done, we know because Valdosta Assistant Director of Utilities Emily Davenport and Valdosta City Council Tim Carroll told us at a meeting Valdosta held at the request of WWALS for interested parties downstream in Florida and from as far away as Atlanta.

On the agenda for the 8:30 AM Monday morning Lowndes County Commission Work Session, item 7.d. Continue reading

Valdosta wastewater improvements ribbon cutting being scheduled for May

Valdosta seems serious about finally opening its new force main and uphill Withlacoochee Wastewater Treatment Plant: they’re scheduling a ribbon cutting for May, a year ahead of the original schedule. According to both City Council Tim Carroll and Engineering Assistant Director Emily Davenport, the EPA has already pressure-tested the relevant lines and the plant, and approved them.

People downstream are rightly concerned at the many years they’ve endured wastewater from Valdosta. And recent schedule slips haven’t helped their perceptions, which is why actually holding Continue reading

Valdosta wastewater fixes schedule update

Thanks, Emily and Henry, and to the City of Valdosta for all your efforts. But could somebody please update the schedule on Valdosta’s website?

Subject: COV Sanitary Sewer System Improvement Update

Good afternoon Chris,

Force-Main-Project-Map--August-2015-001 Thank you for reaching out to me today for an update on the sewer improvements that the City has underway. We have continued to make substantial progress since our meeting back in March that you attended. As discussed then, the city has two major projects underway. One is a $36 million dollar Force Main project and the other is a $23 million dollar Plant Relocation. As of today, the Force Main project is 5 months ahead of the July 2016 schedule and the Plant Relocation is 16 months ahead of schedule. Both projects are tracking a timeline to be complete and online around February 2016. Please note that we have not had any overflow or major permit violations at the wastewater treatment plant since making the emergency repairs in February 2014.

Below is a quick summary of an update I recently received in reference to the sewer manhole overflows: Continue reading

Withlacoochee River sewage spills, Suwannee River Basin flooding study, and Valdosta’s funded plan to fix its problem

Someone referred to the mid-February Old Statenville Road spill in asking:

What’s happening in your watershed? This is the most recent of several sewage overflow issues I’ve been reading about.

Brief answer: this flooding issue is one of many reasons WWALS Watershed Coalition was formed; we’ve been on it since then; the City of Valdosta is being fixed the immediate problem; however there’s a much bigger problem throughout the entire Suwannee River Basin that the Army Corps of Engineers is studying.

Long answer: This has been going on for years, especially starting with the 700-year flood in 2009, which overflowed the City of Valdosta’s Withlacoochee Wastewater Treatment Plant (WWTP) and backed up sewage out of manholes, in addition to rivers and streams running over roads and bridges; see this USGS two-pager on that.

Larry Hanson, Valdosta City Manager, presented to Continue reading

Flooding study presentations by Army Corps in Valdosta 6 May 2014

Received today. -jsq

Good afternoon Mr. Quarterman,

As requested, the date for the U.S. Army Corps of Engineers (USACE) presentation will be on May 6th to Mayor/Council at the work session which begins at 5:30 pm. The City will also have a meeting with the residents and businesses in the USACE project / study area that same night at 6:30 pm at the City Hall Annex – Multipurpose Room.

Continue reading