Valdosta holds ground-breaking on WWTP catch basin 2020-07-21

Long-awaited, since December 2018, with GA-EPD permit in hand since December 2019, today was the groundbreaking for the new catch basin at the entrance to Valdosta’s Withlacoochee Wastewater Treatment Plant (WWTP).

[Ground breaking]
Photo: City of Valdosta, Ground breaking

The catch basin probably would have stopped 2/3 of the December 2018 spills. *The other 1/3 in December 2018 was from city infrastructure not acting as designed, unless 2 million gallons of raw sewage spilling from manholes was in that design.

It would not have done anything to stop the record December 2019 raw sewage spill, which resulted from the Remer Lane Pump Station being left offline and disconnected from the SCADA system.

However, some of the other projects mentioned in the below Valdosta press release may help with both those 2018 and 2019 other problems. It’s good to see Valdosta moving ahead to fix its chronic sewer system infrastructure problems.

FOR IMMEDIATE RELEASE
July 21, 2020
Release #07-21-104

City Breaks Ground on 7.26 Million-Gallon Equalization Basin at Withlacoochee WWTP

On Tuesday, July 21, 2020, The City of Valdosta broke ground on the new Equalization (EG) Basin located at the Withlacoochee Wastewater Treatment Plant.

The new secondary basin will provide more than double the available storage for extended periods of operation at the peak hourly flow thereby reducing the potential for overflows at the Plant. The Project includes a lined 7.26 MG excavated Basin, a new pump station, and an associated gravity pipe and force main.

Since its start-up in 2016, Continue reading