Fluor books huge loses on three failed gas-fired plants, plus two failed nukes

It’s not just GE and Siemens that are “experiencing disruption of unprecedented scope and speed,” power plant builder Fluor finds “The challenges we have experienced over the last two years on gas-fired power projects are inconsistent with the results we have historically achieved.” Maybe you should have bet on sun and wind power, Fluor, Siemens, and GE, instead of fracked methane and nukes.

Fluor and Diablo Canyon nuclear project in California
Photo: Fluor web page on Diablo Canyon nuclear power plant

Copenhaver Construction, Inc., 8 August 2017,

Problems on three gas-fired power plant projects with fixed-price contracts forced Dallas-based Fluor Corp. to book a $124-million charge in 2017’s second quarter.

CEO David. T. Seaton says Continue reading

The handwriting on the wall for Plant Vogtle: electric cars and South Carolina cancels its nuclear project –WWALS to GA-PSC

Sent in PDF via email today.


August 2, 2017

To: Georgia Public Service Commission
244 Washington Street, SW
Atlanta, GA 30334-9052

gapsc@psc.state.ga.us

Re: Electric cars and solar power are here now; South Carolina cancels its nuclear project

Dear Public Service Commissioners and Staff,

Since my letter of July 23, 2017, asking you to stop cost overruns for Plant Vogtle and to require Georgia Power again to buy more solar power,1 there have been major developments that further indicate the desirability of these actions.

Tesla is now shipping its Model 3, which many consider the Model T of the electric car industry, affordable not just to executives, but to the masses. New York City changed in thirteen years from all but one horse-drawn carriages to all but one automobiles in its Easter Parade: 1900 to 1913,2 and not much longer for the rest of the country, after the Ford Model T shipped in 1908.

We’re well past 1900 in the electric vehicle revolution, and that is a rapidly growing market for solar panels on business and house roofs.

In The Hill yesterday:3

South Carolina Electric & Gas Co. (SCE&G) and state-run Santee Cooper both said Monday they would suspend their plan to build two nuclear reactors at the V.C. Summer power plant northwest of Columbia.

The companies cited Continue reading