Tag Archives: Model T

Energy Book co-authors 2018-08-07

We went to Rum 138 to see Merrillee Malwitz-Jipson, when Janet Barrow and I needed to know about the early move of the Sabal Trail pipeline off of the Ichetucknee River. Merrillee, Janet, and I are writing a book about five years working together promoting solar power and opposing that hazardous fracked methane boondoggle.

Festive, Co-authors
Janet Barrow, John S. Quarterman, Merrillee Malwitz-Jipson, 7 August 2018

Three laptops and mounds of paper were used. Almost three months later, we’re still digesting what Merrillee turned up out of her archives. Things we didn’t realize about fossil fuel feints and many solar successes are becoming clear as we compare notes.

Merrillee’s halo seems to be slipping in this picture, and my hat fell off: Continue reading

The handwriting on the wall for Plant Vogtle: electric cars and South Carolina cancels its nuclear project –WWALS to GA-PSC

Sent in PDF via email today.


August 2, 2017

To: Georgia Public Service Commission
244 Washington Street, SW
Atlanta, GA 30334-9052

gapsc@psc.state.ga.us

Re: Electric cars and solar power are here now; South Carolina cancels its nuclear project

Dear Public Service Commissioners and Staff,

Since my letter of July 23, 2017, asking you to stop cost overruns for Plant Vogtle and to require Georgia Power again to buy more solar power,1 there have been major developments that further indicate the desirability of these actions.

Tesla is now shipping its Model 3, which many consider the Model T of the electric car industry, affordable not just to executives, but to the masses. New York City changed in thirteen years from all but one horse-drawn carriages to all but one automobiles in its Easter Parade: 1900 to 1913,2 and not much longer for the rest of the country, after the Ford Model T shipped in 1908.

We’re well past 1900 in the electric vehicle revolution, and that is a rapidly growing market for solar panels on business and house roofs.

In The Hill yesterday:3

South Carolina Electric & Gas Co. (SCE&G) and state-run Santee Cooper both said Monday they would suspend their plan to build two nuclear reactors at the V.C. Summer power plant northwest of Columbia.

The companies cited Continue reading