Tag Archives: Stacie Greco

Alachua County resolution against WFNF 2026-06-09

The most populous county participating in many Suwannee Basin forums, and the first county partly in the St. Johns Basin, Alachua County has passed a resolution opposing Water First North Florida (WFNF) and proposing alternatives.

Before their unanimous vote, the Alachua County Commissioners discussed whether this resolution adequately supported the resolution by the North Central Florida Regional Planning Council (NCFRPC), which represents all twelve counties in the Suwannee River Water Management District.

Well, the Alachua County resolution doesn’t say anything about desalination, nor anything else for Jacksonville to reduce its groundwater withdrawals. It recommends limiting irrigation to only one day a week, apparently only for Alachua County.

Still, the 800-pound gorilla has spoken, and its last recommendation is:

7) evaluate alternatives to the Water First North Florida Project along with filtration and siting strategies for beneficial re-use of reclaimed water from Jacksonville.

[Alachua County resolution against WFNF 2026-06-09, Stacie Greco, landscape irrigation]
Alachua County resolution against WFNF 2026-06-09, Stacie Greco, landscape irrigation

For much more about WFNF, see:

https://wwals.net/issues/wfnf

11:30 AM, Tuesday, June 9, 2026, Alachua County BOCC Meeting Agenda:

  1. Lower Santa Fe and Ichetucknee Rivers Implementation Strategy/Water First North Florida Project Resolution – 26-00395
Continue reading

WFNF not done yet –Florida Alligator 2026-06-14

More on how WFNF is not done yet, including that contributing projects are still going.

Cost is one of many reasons for the massive public opposition to Water First North Florida (WFNF), the plan to pipe treated wastewater from Jacksonville into the Suwannee River Basin.

The WFNF cost estimate was $1 billion in July 2025, but had ballooned to $1.1 billion by February 2026. That’s 10% inflation in six months.

Even that higher estimate expressly does not include the cost of the pipeline or eminent domain, not to mention likely lawsuits.

Another reason is that few people trust JEA to clean up the wastewater or to keep the pipeline system working without failures.

Another is that nobody got to vote on WFNF except the unelected boards of JEA and the St. Johns and Suwannee River Water Management Districts (SJRWMD and SRWMD).

[WFNF not done yet --Florida Alligator 2026-06-14, Stacie Greco, Alachua County, Sarah Younger, SSGSCFL]
WFNF not done yet –Florida Alligator 2026-06-14, Stacie Greco, Alachua County, Sarah Younger, SSGSCFL

Much more about WFNF here:

https://wwals.net/issues/wfnf

Julianna Bendeck, the independent florida alligator, June 14, 2026, Why the Water First North Florida project may not be done just yet: The state cancelled the $1 billion aquifer recharge proposal amid drought conditions,

Although state officials abandoned the original Water First North Florida proposal, research associated with the project continues.

Continue reading