Nine Riverkeepers say FERC’s Sabal Trail SEIS unacceptable; request pipeline shutdown

FOR IMMEDIATE RELEASE

Hahira, Georgia, November 21, 2017 — Factually incorrect, failing to account for LNG export or solar power, and irresponsible for not finding or creating a method for attributing environmental effects to greenhouse gases, as the DC Circuit Court had instructed the Federal Energy Regulatory Commission (FERC) to do: that’s what nine Riverkeepers called FERC’s Supplementary Environmental Impact Statement (SEIS) yesterday; see their letter to FERC. The nine include all the Riverkeepers in the path of Sabal Trail and all parts of the Southeast Market Pipelines Project (SMPP) plus others in all three states invaded by those pipelines, Florida, Georgia, Alabama, plus Oklahoma, where the SMPP instigator, Florida Power & Light (FPL), owns a fracking field, The nine, who support fishable, swimmable, drinkable water, pointed out that all of FPL’s original excuses for Sabal Trail have been proven incorrect, and asked FERC to shut it down.

Green is Sabal Trail; Transco and FSC in black, SMPP
Sabal Trail in green, Transco and FSC in black, in Sierra Club interactive map of gas pipelines.

The Riverkeepers weren’t buying FERC’s ignorance: Continue reading

Eight Riverkeepers oppose FERC’s inaccurate and inadequate Sabal Trail SEIS and request pipeline shutdown 2017-11-20

Filed today as FERC Accession number 20171120-5130, “Opposition to the incorrect and inadequate FERC Sabal Trail SEIS and request for pipeline shut down by Suwannee Riverkeeper (WWALS) and Apalachicola, Ogeechee, Grand, Choctawhatchee, Chattahoochee, Indian, and Flint Riverkeepers.” (Or see WWALS PDF.)

Shut it down, From: The undersigned Waterkeepers

Date: November 20, 2017

To: Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
888 First Street NE, Room 1A
Washington, DC 20426

Re: We oppose the incorrect and inadequate FERC Sabal Trail SEIS
FERC Docket Numbers CP14-554-002, CP15-16-003, and CP15-17-002

On September 27, 2017, the Federal Energy Regulatory Commission (FERC) published a draft Supplementary Environmental Impact Statement (SEIS).[1] That SEIS was in response to the August 27, 2017 DC Circuit Court decision[2] regarding FERC’s previous approval of Certificates of Convenience and Necessity for the three parts of the Southeast Markets Pipeline Project (SMPP), which are the Transcontinental Gas Pipe Line Company, LLC’s (Transco) Hillabee Expansion Project in Docket No. CP15-16-000; Sabal Trail Transmission, LLC’s (Sabal Trail) Sabal Trail Project in Docket No. CP15-17-000; and Florida Southeast Connection, LLC’s (FSC) Florida Southeast Connection Project in Docket No. CP14-554-000. The judges ordered:

“The orders under review are vacated and remanded to FERC for the preparation of an environmental impact statement that is consistent with this opinion.“

The draft SEIS issued by FERC is clearly not consistent with the court’s opinion for the following reasons:

  1. The SEIS is factually incorrect in stating that: Continue reading