Force main and the new WWTP on line by May!
More extensive overflows than usual last weekend, and now more extensive information about them,
in
the update Tim Carroll promised,
on the City of Valdosta website as
City System Impacted by Severe Storms and Regional Watershed.
It even starts with schedule details, which say they’re
ahead of
the schedule I previously posted.
This report’s table of overflows has start and stop times and amounts, with the Creeks affected.
It still doesn’t say which river basin they go into. Knights Creek flows into Mud Creek, which goes into the Alapahoochee, Alapaha, and Suwannee Rivers. All the others end up in the Withlacoochee and the Suwannee Rivers. And there are still some unanswered questions. But getting the force main and the new WWTP on line by May is a very good development.
The City of Valdosta is ahead of schedule and plans to bring online nearly $60 million in wastewater system improvements next month. The $35 million Force Main project and the $23 million new Withlacoochee Wastewater Treatment Plant (WWTP) are both ahead of schedule, and bringing them both online cannot come a day too soon for the city.
“We are pleased to be in the final stages of construction on both projects. Testing is underway now with full startup expected in late May,” according to Director of Utilities Henry Hicks. “We are also pleased that these projects and other awarded sewer collection system improvement projects underway will resolve all the areas of the city impacted by reoccurring overflows that often follow heavy rains and regional flooding.”