Update 2020-12-23: Pictures of the repair in progress.
Lowndes County is fixing the June 8, 2020, sinkhole at the Bevel Creek Lift Station in a Floridan Aquifer recharge zone, with $82,000.00 to replace two manholes, to discuss at its Work Session 8:30 AM Monday morning, with voting at its 5:30 PM Regular Session Tuesday, June 23, 2020.
The county’s agenda sheet says:
Due to extensive flooding and undermining, the manhole before Bevel Creek lift station collapsed on June 8, 2020 creating an emergency situation. After accessing the problem it was determined the most feasible and economical method of repair was to replace two manholes and redirect the flow. RPI Underground submitted a quote not to exceed $82,000 to make the repairs. Staff recommends approval of the Bevel Creek manhole emergency repair by RPI Underground not to exceed $82,000.00.
Photo: Terry Richards, The Valdosta Daily Times,
Heavy rains cause problems in Lowndes 2020-06-08.