GA-EPD cites Suwannee Riverkeeper and US EPA against TPM titanium mine near Okefenokee Swamp 2019-09-12

GA-EPD told USACE the mining application is incomplete, asked for comments to be reopened, and cited Suwannee Riverkeeper and Georgia River Network:

“Understanding that groundwater hydrologic effects associated with the Twin Pines project have been a central concern expressed by federal resource/regulatory agencies, NGOs (e.g. the Suwannee Riverkeeper and Georgia River Network), and the public at large, we respectfully submit that the 404/401 permit application as submitted thus far is not complete since it lacks full information and findings regarding hydrogeologic factors on site and post-project effects to hydrogeology/groundwater. We feel that it is inappropriate and premature to close the project comment window when such notable elements of the environmental documentation for this project have not yet been made available. documentation which we at GaEPD judge to be important to our review of this project.”

[the 404/401 permit application as submitted thus far is not complete]
the 404/401 permit application as submitted thus far is not complete

This was revealed by USACE in a Public Notice of September 17, 2019. So far, this is the only update posted by the Corps since it closed comments on September 12, 2019.

It also includes comments by U.S. EPA, also saying the application is incomplete, and also cited by GA-EPD. EPA cites cumulative effects and notes numerous lacking documents and studies. EPA concludes:

“Due to the potential for the proposed Twin Pines Minerals mine to adversely affect the hydrology of the Okefenokee NWR, the EPA believes that there is the potential for this project as proposed to cause adverse effects to water quality and the life stages of aquatic life or other wildlife dependent on aquatic systems. The EPA finds that this project, as proposed, may result in substantial and unacceptable impacts to aquatic resources of national importance, as covered in Part IV. paragraph 3(a) of the August 1992 Memorandum of Agreement between the EPA and the Department of the Army regarding CWA Section 404(q).”

Apparently USACE is at least listening to the public and the public and NGOs such as Suwannee Riverkeeper.

You can still send in comments. The Corps won’t say they will read them, but they explicitly won’t say they won’t read them, so keep sending them in, and publish them on social media, as op-eds, etc. Continue reading

Comments: 20,338 on titanium mining near Okefenokee Swamp –USACE 2019-09-12

If this and the 27 news articles on radio, TV, and newspapers in Georgia and Florida, several of them carried by Associated Press across the country, plus the ten op-eds and three editorials, is not enough to establish controversy, I wonder what is. Maybe still more comments and news articles and social media?

[Public Notice: 20,338 comments]
Public Notice: 20,338 comments
PDF

Nedra Rhone, Atlanta Journal-Constitution, 13 September 2019, Mining proposal near Okefenokee draws more than 20K comments from public

The Suwannee Riverkeeper, on Thursday, sent 22 pages of questions to the Corps and the Georgia Department of Environmental Protection asking the agency to deny the permit. The Riverkeeper joined the SELC and other organizations and individuals in asking the Corps to prepare an Environmental Impact Statement, the highest level of analysis available when a proposed federal action may significantly affect the quality of the human environment.

Also in that AJC story:

Commenters expressed concerns ranging from the acres of wetlands that would be lost to what they considered inadequate studies conducted to determine the potential impact of the mine.

In a letter to the Corps, the Southern Environmental Law Center said Continue reading

Deny or EIS, titanium mining near Okefenokee Swamp –Suwannee Riverkeeper for WWALS 2019-09-12

Sent just now as PDF. You can still send in your comments today.

[Who wants to boat, fish, bird, or hunt next to a strip mine?]
Who wants to boat, fish, bird, or hunt next to a strip mine? PDF


September 12, 2019

To: Col. Daniel Hibner, Commander, U.S. Army Corps of Engineers, Savannah District
       Attention: Ms. Holly Ross,  holly.a.ross@usace.army.mil
       1104 North Westover Boulevard, Suite 9, Albany, Georgia  31707

Cc: Stephen Wiedl, Wetlands Unit, stephen.wiedl@dnr.ga.gov
       Georgia Department of Natural Resources, Environmental Protection Division,
       Water Protection Branch, 7 Martin Luther King, Jr. Drive, Atlanta, GA 30334

Re: Applicant: Twin Pines Minerals, LLC, Application Number: SAS-2018-00554

Dear Colonel Hibner,

Suwannee Riverkeeper for WWALS Watershed Coalition (WWALS) asks USACE:

  • to reject the subject Application from Twin Pines Minerals (TPM), given the inappropriate location which would over the years move ever closer to the Okefenokee Swamp, which is the headwaters of the Suwannee and St. Mary’s Rivers, combined with the numerous omissions from the Application regarding the wide hydrogeologic, water quality, ecologic, and economic ramifications of the proposed mining, and the numerous other mines relevant to the proposal.

If USACE continues to process the Application, WWALS requests USACE:

  • to require a complete hydrogeological assessment and report, a full Environmental Impact Statement (EIS), and an economic analysis, with all three covering all the relevant features, mines, and applications in south Georgia and north Florida, including at least those outlined in this letter.
  • to accept comments until at least ninety days after all these documents are submitted to USACE and distributed to the public, preferably on USACE’s website, without requiring site visits to Albany to get them.
  • to hold public hearings in Georgia and Florida for further independent input and review after sufficient time (months or years) for independent third-party review.

The proposed Charlton County, Georgia, TPM mine site is hydraulically upgradient from the Okefenokee Swamp and within close proximity to the boundary of the Okefenokee National Wildlife Refuge (ONWR), with its 600,000 visits per year for boating, birding, and fishing, with more than $60 million annual economic effects including hundreds of jobs supported directly or indirectly, plus hunt clubs surrounding the Swamp. The Swamp provides ecosystem services of great economic values, including storm protection, water quality provisioning, support for nursery and habitat for commercial fishing species; and carbon storage, plus those hunt clubs depend on the Swamp. Any pollution of the Swamp or change in surface or groundwater levels could adversely affect not only ONWR and nearby areas, but also the Okefenokee Swamp Park (OSP) near Waycross, in Ware County, GA, and Stephen C. Foster State Park (SCFSP) in Charlton County, via Fargo in Clinch County. Visitors come from Jacksonville, Florida, Brunswick and Valdosta, Georgia, and from much farther away to visit the Okefenokee Swamp. The Swamp is a treasure to the entire nation and the world.

The stigma of a strip mine next to the swamp could cause people to turn away, taking their dollars with them. Who wants to boat, fish, bird, or hunt next to a strip mine?

Continue reading

PCS Phosphate Mine dragline access permit application SAJ-1984-04652 2019-10-15

See also: Hamilton County Planning Commission wants conditions on Nutrien phosphate mine permit renewal 2023-03-28.

It may be useful to keep tabs on last year’s USACE expansion application of the PCS (now Nutrien) phosphate mine in Hamilton County, FL.

Jacksonville District, U.S. Army Corps of Engineers, SAJ-1984-04652 (MOD-JPF), Published Oct. 15, 2018, Expiration date: 11/14/2018

[Location Map]
Location Map
PDF

Here are the rest of the maps from that document. Continue reading

Need EIS, public hearings –Okefenokee Swamp Park to USACE about titanium mine 2019-08-22

Excellent comments from Okefenokee Swamp Park, requesting at least three public hearings by the Army Corps, plus independent research, in addition to a full Environmental Impact Statement. When I received them from Dr. Clark last night, he asked me to circulate them widely; see also PDF.

[About OSP]
About OSP

Continue reading

Charlton County Resolution supporting the proposed titanium mine near the Okefenokee 2019-08-15

This is the resolution passed Thursday week before last by the Charlton County Commission, collected today from the County Clerk.

You can still comment to the U.S. Army Corps of Engineers, which actually has authority over the mine permit application.

[Twin Pines Materials, LLC]
Twin Pines Materials, LLC

BOARD OF COMMISSIONERS
CHARLTON COUNTY, GEORGIA
PROCLAMATION OF SUPPORT OF
TWIN PINE MATERIALS, LLC

WHEREAS, the Charlton County Board of Commissioners is the governing authority of Charlton County, Georgia;

WHEREAS, economic development and quality, Continue reading

Deadline Extended to September 14 12 on mining proposal near Okefenokee NWR 2019-07-19

Update 2019-07-22: Corrected headline to match extension date in GPB story. See also Charlton County, GA, BOCC 2019-07-18.

I asked the Charlton County Commission just yesterday to ask the Corps for an extension, and numerous other people and organizations have done so. The Corps has already responded.

Emily Jones, Georgia Public Broadcasting, 19 July 2019, Army Corps Extends Comment Deadline On Mining Near Okefenokee,

The Army Corps of Engineers is extending the deadline for public comments on a proposal to mine for minerals near the Okefenokee National Wildlife Refuge.

The new deadline is September 12, an additional 30 days from the original deadline of August 13.

Environmental groups were calling for the deadline extension.

Since there’s nothing on the Corps’ Public Notices website about that, I asked her how she knew. She said Senior USACE Public Affairs Officer Billy Birdwell, 912-652-5014. So I called him.

Billy Birdwell received a Certificate of Appreciation
Photo: USACE. Continue reading

Complete permit application, Twin Pines Minerals 2019-07-17

The complete 565-page permit application by Twin Pines Minerals, SAS-2018-00554, is now on the WWALS website.

News about it is all over North America, with more coming out daily.

You can go ahead and send in comments to the Army Corps of Engineers or to the Georgia Department of Natural Resources.

[Twin-Pines-Individual-Permit-Application--complete-0006]
Twin-Pines-Individual-Permit-Application–complete-0006

You can retrieve the complete application from Continue reading

GPB on mining proposal near Okefenokee NWR 2019-07-15

My vegetable buyer from St. Mary’s, GA, said “I heard you on the radio this morning.” Notice the map Georgia Public Broadcasting posted says “Phase I” in U.S Army Corps of Engineers Application SAS-2018-00554. The company actually owns land northwards all the way up next to the swamp.

[Phase I location Map]
Phase I location Map

Emily Jones, GPB Radio News, 15 July 2019, Mining Proposed Near Okefenokee National Wildlife Refuge,

An Alabama company wants to mine for heavy minerals near the Okefenokee National Wildlife Refuge in southeast Georgia.

The proposal from Twin Pines Minerals called for Continue reading

Titanium mine near Okefenokee NWR 2019-07-12

Update 2019-07-18: The complete application is now on the WWALS website; you can comment now.

Friday, July 12, 2019, the U.S. Army Corps of Engineers published a Public Notice for Application SAS-2018-00554 for a titanium mine southeast of the Okefenokee National Wildlife Refuge (NWR). Thursday I attended a meeting at the Okefenokee NWR near Folkston about that, and I met with agents of the miners back in April. The application is about the little purple area on this map they showed us at the end of April:

[Context]
Context

But that’s not the whole story; see below. Today this mine proposal is on the agenda for the WWALS board meeting.

Here are some things the application doesn’t tell you: Continue reading