Tag Archives: EQ

Valdosta holds ground-breaking on WWTP catch basin 2020-07-21

Long-awaited, since December 2018, with GA-EPD permit in hand since December 2019, today was the groundbreaking for the new catch basin at the entrance to Valdosta’s Withlacoochee Wastewater Treatment Plant (WWTP).

[Ground breaking]
Photo: City of Valdosta, Ground breaking

The catch basin probably would have stopped 2/3 of the December 2018 spills. *The other 1/3 in December 2018 was from city infrastructure not acting as designed, unless 2 million gallons of raw sewage spilling from manholes was in that design.

It would not have done anything to stop the record December 2019 raw sewage spill, which resulted from the Remer Lane Pump Station being left offline and disconnected from the SCADA system.

However, some of the other projects mentioned in the below Valdosta press release may help with both those 2018 and 2019 other problems. It’s good to see Valdosta moving ahead to fix its chronic sewer system infrastructure problems.

FOR IMMEDIATE RELEASE
July 21, 2020
Release #07-21-104

City Breaks Ground on 7.26 Million-Gallon Equalization Basin at Withlacoochee WWTP

On Tuesday, July 21, 2020, The City of Valdosta broke ground on the new Equalization (EG) Basin located at the Withlacoochee Wastewater Treatment Plant.

The new secondary basin will provide more than double the available storage for extended periods of operation at the peak hourly flow thereby reducing the potential for overflows at the Plant. The Project includes a lined 7.26 MG excavated Basin, a new pump station, and an associated gravity pipe and force main.

Since its start-up in 2016, Continue reading

Three weeks to comment on GA-EPD Valdosta wastewater Consent Order

Update 2023-11-09: GA-EPD Consent Order on Valdosta for One Mile Branch fish kill and sewage spills 2023-09-15.

Update 2020-05-10: Send your comment on GA-EPD Valdosta wastewater Consent Order –Albany Herald.

FOR IMMEDIATE RELEASE (see also PDF)

Three weeks to comment on GA-EPD Valdosta wastewater Consent Order

Hahira, GA, May 4, 2020 — May 27th is the deadline to comment on the Enforcement Order the Georgia Environmental Protection Division (GA-EPD) finally issued on Valdosta for sewage spills. For decades, Valdosta has spilled wastewater into the Withlacoochee River. People downstream, even on the Suwannee River all the way to the Gulf, worry about fishing, swimming, or even boating and some even say their wells are contaminated by fecal bacteria from these spills. Many had hoped that Valdosta’s big spills were over in 2016 with the new Withlacoochee Wastewater Treatment Plant uphill out of the flood plain, plus a Force Main with two Pump Stations. Valdosta says it has spent about $80 million on water system improvements. Yet the spills continued. The Order also reveals a massive fish kill.

[Photo 2: Dead largemouth bass in Sugar Creek below Bay Tree Road.]
Photo 2: Dead largemouth bass in Sugar Creek below Bay Tree Road.

“The December 2019 spill was the biggest yet, with no rain, and nothing actually broke. It was a massive failure of supervision,” said Suwannee Riverkeeper John S. Quarterman. “Citizens and elected and appointed officials in Georgia and a dozen counties in Florida demanded something be done.”

This Enforcement Order includes the most popular request, a fine, plus many requirements for management and technology.

“Well, I’m glad they are doing the enforcement order, requiring them to get the fixes in place,” said Deanna Mericle of Hamilton County, Florida, who was among the WWALS members who met with the City of Valdosta back in 2015 about these same sewage issues. She added, “I’m not sure what the $122,000 will be used for, but the fine seems small. I just want the problem fixed for good if possible.”

The Order addresses much (but not all) of what Suwannee Riverkeeper asked GA-EPD to do: https://wwals.net/?p=50979 For example, it requires the City to test water quality all the way down to the state line. One thing it does not include is any requirements for reimbursing downstream well and river testing expenses.

“It’s good to see that the EPD is FINALLY taking this issue seriously!” said Suzy Hall, WWALS Testing Committee Chair. “I can’t help but feel WWALS’ diligence in testing has been a big part of this action, and must continue regardless of any order for the City to conduct testing.”

The entire 93-page Order is on the WWALS website, here:
https://wwals.net/pictures/2020-04-13–ga-epd-vld-enforcement-order

“This Order has been a long time coming. It includes an outline of a sad history of mistakes and neglect. I hope the Order will finally get the City’s attention,” said Dr. Tom Potter, WWALS Science Committee Chair and taxpayer of the City of Valdosta.

Send your comments by Wednesday, May 27, 2020, to:
   Mr. Lewis Hays
   Manager, Watershed Compliance
   Environmental Protection Division
   2 Martin Luther King Jr. Drive SE, Suite 1152 East
   Atlanta, GA 30334
   Lewis.Hays@dnr.ga.gov
   404-463-4953

About WWALS: Founded in June 2012, WWALS Watershed Coalition, Inc. (WWALS) advocates for conservation and stewardship of the Withlacoochee, Willacoochee, Alapaha, Little, Santa Fe, and Suwannee River watersheds in south Georgia and north Florida through education, awareness, environmental monitoring, and citizen activities. John S. Quarterman is the Suwannee Riverkeeper®, which is a staff position and a project of WWALS as the member of Waterkeeper® Alliance for the Suwannee River Basin.

Contact: John S. Quarterman, Suwannee Riverkeeper contact@suwanneeriverkeeper.org
WWALS Watershed Coalition
850-290-2350, 229-242-0102
PO Box 88, Hahira, GA 31632

===

 -jsq, John S. Quarterman, Suwannee RIVERKEEPER®

You can join this fun and work by becoming a WWALS member today!

GA-EPD Enforcement Order for Valdosta wastewater with fine 2020-04-13

Update 2020-05-04: Press Release, Three weeks to comment on GA-EPD Valdosta wastewater Consent Order.

Much of what many people requested is in this Enforcement Order EPD-WP-8904 of the Public Notice of April 27, 2020.

[Photo 1: Site where sewage flowed out of manhole into Sugar Creek.]
Photo 1: Site where sewage flowed out of manhole into Sugar Creek.

Perhaps the most popular request, a fine, is included. As a Project In-Lieu of Penalty (PIP) stream testing is required, three times a week, down to the state line. Plus: “The Respondent shall post all the results of biological monitoring required after major spills to its website and to the Georgia EPD Adopt-A-Stream website within one business day of receipt of the results.”

All 250 sewer line creek crossings must be inspected by drone crews.

Valdosta must notify many Florida agencies, plus in Georgia Lowndes Health and Brooks EMA.

Other things are missing. WWALS is not on that notification list, for example.

[Photo 2: Dead largemouth bass in Sugar Creek below Bay Tree Road.]
Photo 2: Dead largemouth bass in Sugar Creek below Bay Tree Road.

And the Order reveals some Valdosta violations the public never knew about, such as a massive fish kill in December 2019. The cost of that calculated by GA-DNR Wildlife Division seems inadequate, since it doesn’t take into account people being unwilling to fish on the Withlacoochee River, for example.

If you think there should be more or changed requirements, the Public Comment period ends May 27, 2020.

Send comments to: Continue reading

Valdosta WWTP spilled millions of gallons and didn’t tell the public for days 2017-01-25

Update 2017-01-30:

Valdosta also didn’t tell the public all day after the spill stopped, and then posted something that’s flat not true.

I just called Valdosta WWTP Superintendent John Waite, as it says to do on the city’s PR posted Wednesday, January 25, 2017 5:09:00 PM, Withlacoochee Plant Warranty Repairs Underway, which says “The plant is under warranty and the repairs will be complete by end of day Jan. 25 at no cost to the city.” Meanwhile, the Valdosta Daily Times posted yesterday evening City sewage spill stopped.

I asked Superintendent Waite when the spill stopped.

Answer: Continue reading

And also a Valdosta WWTP spill 2017-01-24

After I posted about the three manhole spills, I discovered Valdosta also announced a spill at the Withlacoochee Wastewater Treatment Plant (WWTP).

I just called Scott Fowler at Valdosta Utilities, and he explained:

The leak is from the jet mix pipe that comes back from the influence and pushes back to the EQ [Equalization Tank]. When they put the pipe in with its industrial strength rubber seal, they pressure tested it, and it held. But the seal blew this weekend. They have cameras there to watch it.

Fowler said they also going to have a camera at Wainwright Drive, where one of the other three spills, the ones from manhole covers, happened.

I pointed out to Fowler that the Valdosta PR about the WWTP spill says they detected it Sunday January 22nd, yet it wasn’t published on the city’s website until Tuesday January 24th after 6PM. He said that’s due to Continue reading