Tag Archives: Titusville

Need Show Cause for NFE Miami LNG, Strom LNG, etc. –WWALS to FERC 2021-07-30

I wondered why we were suddenly getting media inquiries about a letter WWALS sent to FERC two weeks ago. Yesterday FERC got around to posting it. Weirdly for a letter about Florida, in the docket for a Puerto Rico Liquid Natural Gas (LNG) facility. Well, we did cite FERC’s March 2021 Order in that docket as a precedent.

Interestingly, it’s marked:
Non-decisional: No

Does that mean FERC is willing to entertain what we asked? Send SHOW CAUSE letters to all five Florida facilities? Or revoke FERC’s 2015 abdication of oversight over inland LNG export facilities?

As the letter says, we are not fans of FERC. But no FERC environmental oversight turns out to be worse than FERC.

WWALS to FERC 2021-07-30

Accession Number 20210817-4000 as “Comments of WWALS Watershed Coalition re NFE Miami LNG under CP20-466.”

The letter references the 2015 FERC decision that it did not have jurisdiction over inland LNG facilities. That decision is Pivotal LNG, Inc., 151 FERC ¶ 61,006, (2 April 2015). Then-Commissioner Norman Bay dissented, writing in part:

Here, the majority acknowledges that “liquefaction facilities operated by Pivotal and its affiliate … [will] produce liquefied natural gas that [will] ultimately be exported to foreign nations by a third party” and that such foreign sales must be made pursuant to an export license from DOE.5 There can be little doubt, therefore, that the facilities will be involved in the “exportation of natural gas in foreign commerce.”

Until FERC revokes that 2015 abdication of oversight over inland LNG export facilities, the least it can do is to send SHOW CAUSE orders to each such facility demanding to know why it should not be under FERC oversight.

[Need Show Cause; Map of LNG export operations]
Need Show Cause; Map of LNG export operations

Incidentally, FERC Hotline Support replied about Nathaniel Davis: “He no longer works at FERC.” I had to forward the letter to Janel Burdick, the Deputy Director, Office of Enforcement, who is now also Acting Director. Does anybody know what happened to cause that personnel change at FERC? Continue reading

Titusville LNG denied by PHMSA 2018-10-02

Two years later, PHMSA still lists New Fortress Energy’s Titusville LNG facilty as Denied.

The missing piece in NFE’s application? A “Draft Environmental Assessment (DEA)” with “site drawings, maps, and other supporting documents.”

Funny how when a liquid natural gas (LNG) facility has to submit these things, often it can’t.

With the LNG market overseas cratering, maybe this one will stay dead. But we must keep watch to be sure it does not reappear, zombie-like, right in the middle of Florida’s Atlantic coast, able to ship by truck and rail as far as Jacksonville and Miami, as well as overseas.

[LNG--TITUSVILLE--PHMSA--LETTER-DENYING-APPLICATION--10.02.18-0001]
LNG–TITUSVILLE–PHMSA–LETTER-DENYING-APPLICATION–10.02.18-0001
PDF

The denial letter is Continue reading

The illusion of pipeline invincibility is shattered –WWALS Brief to FERC in Sabal Trail Rehearing

Let’s cut to the chase in the letter we filed with FERC yesterday:

11. Historic new circumstances add up

The sun never set on the British Empire. Until it did.

No one circumstance ended that Empire, but it is easy to point at major events that accelerated its demise, such as the independence of India and the Suez Incident. Its fall started after the illusion of its invincibility was shattered by Gandhi’s campaign of civil disobedience and other events such as World War II.

The illusion of invincibility of the inland colonial empire of pipelines has been shattered by recent court orders about the ACP, DAPL, and others, and especially by the shut down of the Dakota Access Pipeline and the shuttering of the Constitution Pipeline and the Atlantic Coast Pipeline. All of those pipelines were expected to be built, and DAPL actually was built before being ordered to shut down and empty. Now the world knows that pipelines are not inevitable.

All these pipeline projects, like Sabal Trail, were opposed by nonviolent protests and political and legal actions. All those methods of opposition, combined with the sea-change in progress to renewable energy, eventually added up to a new and significantly different world than that in which Sabal Trail was permitted or re-permitted.

The shut down of DAPL and the abandonment of ACP as well as the court rejection of tolling orders make it a new world even since FERC’s June 19, 2020, Order granting a rehearing on Sierra Club’s motion.

FERC should initiate a new [Supplemental Environmental Impact Statement] EIS that should take into account Sabal Trail’s own track record of leaks and sinkholes, as well as leaks and accidents from [Liquid Natural Gas] LNG export and LNG transport in rail cars, the speeding demise of fossil fuels as evidenced by record low LNG export prices and bankruptcies of frackers, the court rejections of DAPL, ACP, and tolling orders and how much of Sabal Trail could never have been built through environmental justice communities without tolling orders, the coronavirus pandemic, and the rapid rise of renewable solar, wind, and battery power as evidenced by FPL and Sabal Trail partners Duke and NextEra, as well as by FERC’s own numbers. All of those new and significant circumstances make pipelines such as Sabal Trail toxic stranded assets, dangerous to the bank accounts of their investors, as well as to the environment, justice, and human health.

Conclusion

For the reasons stated above, WWALS asks FERC to grant Sierra Club’s motion for stay of the Commission’s letter order of April 22, 2020, to halt Sabal Trail Phase II, and to commence a Supplemental Environmental Impact Statement (SEIS) taking into account all of the above new and significant circumstances.

[Third-party inspection, recission, stay, SEIS]
Third-party inspection, recission, stay, SEIS

For those who are not familiar with tolling orders, they are basically how, after the Federal Energy Regulatory Commission (FERC) gives federal eminent domain to a private pipeline company, FERC lets that pipeline company take land before any payment to the landowner or even any agreement is reached. Without tolling orders, it’s not clear the FERC will ever get another pipeline built.

Here’s a longer explanation. Continue reading