No five-month extension for Sabal Trail, FERC 2018-01-26

Instead of giving Sabal Trail a five-month extension, FERC should revoke Sabal Trail’s Certificate of Convenience and Necessity, as the U.S. District Court already ordered. Sabal Trail no longer has the customers for 90+% of its gas on which that FERC’s February 2 Order depended, not since Sabal Trail dropped Duke Energy Florida (DEF) from its customer index on New Year’s Day.

Tillerson and Czaputowicz
Secretary of State Rex Tillerson (L) and Polish Foreign Minister Jacek Czaputowicz shake hands during a joint press conference after their meeting in Warsaw on January 27, 2018. / AFP / Wojtek RADWANSKI

It’s time to stop the fossil fuel industry using Sabal Trail as a political tool to undermine the overall energy stability and security of the U.S. southeast for the profit of a few companies from Texas and Canada. Just like the U.S. State Department recommends for Europe, FERC should seek to diversify energy supplies by getting on with solar power onshore and wind power offshore in the Sunshine State, Georgia, and everywhere else.

Suwannee FGT M&R Yard KMI JEP, Suwannee County
Photo: John S. Quarterman for WWALS on Southwings flight June 21, 2016, of site of Sabal Trail Suwannee County M&R Station connecting to Florida Gas Transmission (FGT).

What’s that “one additional M&R facility,” Sabal Trail? Is it the one in Suwannee County to feed your fracked gas through Continue reading

Critical Notice of Sabal Trail Hildreth Compressor outage 2018-01-24

Why are you having an outage at your Hildreth Compressor Station in Suwannee County, Florida, Sabal Trail? And are there continuing stink leaks at your site without a compressor at Dunnellon, Florida in Marion County? Meanwhile, you’re still shipping nothing. For that $3 or $4 billion, much more electricity from solar power could be online right now in Florida, shutting down gas power plants instead of building them.

Hildreth Compressor Station,
Photo: by anonymous, of Sabal Trail Hildreth Compressor Station site, 2016-12-12.

Thanks to eagle-eye WWALS member Janet Barrow for spotting Continue reading

Same Excuse: FERC rubberstamps PennEast like Sabal Trail 2018-01-19

Precedent agreements for 90+% of the pipeline’s capacity was FERC’s excuse for PennEast yesterday, the same as for Sabal Trail two years ago. Yet Sabal Trail apparently already lost 4/7 of its supposedly solid customer base and is not even shipping any gas. Even a dissenting FERC Commissioner spelled out that such shaky “need” does not justify environmental damage nor invasion of property rights through federal eminent domain. Sure, Commissioner LaFleur, we should trust PennEast with the Delaware River like FERC told us to trust Sabal “Sinkhole” Trail about the Suwannee River?

FERC Commissioner Richard Glick On New Year’s Day Sabal Trail removed Duke Energy Florida (DEF) from its customer index. On November 14, 2017, Sabal Trail’s gas flow dropped to zero, and Sabal Trail increased its Uncommitted Capacity by 300,000 Dekatherms per day, exactly the same as DEF formerly contracted for, and thirty days after DEF’s initial contract expired. That leaves FPL as Sabal Trail’s only customer, with its 400,000 DTH/day. Four sevenths of of 93% is only about 53%, which is not even the 75% Commissioner Richard Glick also mentioned in in his Friday dissent from the 4:1 FERC rubberstamp of the PennEast pipeline, which also happens to be a feeder for Sabal Trail through Transco. Meanwhile, during freezing weather in Florida, Sabal Trail shipped zero gas for much of November and January (and hardly any in December): how is that need?

Lost Duke Energy Florida, Flow
Lost Duke Energy Florida, Sabal Trail?

No Balance

Commissioner Glick’s opening paragraph also sums up the recent WWALS motion to FERC to reject, shut off, and revoke Sabal Trail: Continue reading

Sabal Trail to Gulfstream, Martin County, and where? 2018-01-18

Sabal Trail ramped up the last couple of days, to 196 thousand Dekatherms/day (MDTH/day) today. Most of that they’re shipping out to Gulfstream at Osceola. with a bit through FSC to FPL’s Martin County power plant, and the rest somewhere.

Why now? During the last cold spell, they spiked briefly in the first week of January, but dropped back to zero while there was snow on the ground in Florida.

So what are they up to now?

This month (2018-01-01 -- 2018-01-18), TIMELY

From the various pipeline’s FERC-required daily postings, Gulfstream shows Continue reading

Less than Zero: Sabal Trail Gas 2018-01-10

If Sabal Trail gas isn’t needed continuously when there was snow in Florida during the coldest week of the winter, when is it needed? This week when it’s warm Sabal Trail gas went to less than zero (-2 MDTH/day Nominated Capacity). So apparently it’s needed never. Shut it down.

This month 2018-01-01 to 2018-01-10, Graph

This month 2018-01-01 to 2018-01-10, Graph

To review, Sabal Trail’s gas dropped to zero November 14, 2017, and stayed there for seventeen days, before going up slightly, dropping back to zero, bursting in the first week of January, shipping most of that gas to other pipelines and peaking power plants, then dropping back to almost nothing and then less than nothing. Continue reading

Sabal Trail gas into Gulfstream, 2018-01-1-6

It’s a shell game: much of Sabal Trail’s early January burst to maximum capacity went back out through the Gulfstream pipeline in Osceola County, which sent it to a Duke Energy Florida peaker plant in Intercession City and to Florida Gas Transmission (FGT). Presumably some of Sabal Trail’s peak went directly to FPL, but some of it apparently went through Gulfstream to get there. Yet apparently none of it was needed, since in the coldest week of the winter so far, Sabal Trail went back down to almost zero.

100% above ave: IN Sabal Trail Osceola, out Duke Intercession City and FGT Hardee, Charts

Using data from the various pipeline’s own FERC-required daily information postings, Gulfstream shows “SABAL TRAIL – OSCEOLA IN MP 60.25” suddenly bumping up Continue reading

Flash in the pan, Sabal Trail? 2018-01-06

Where did that gas go for that one day, Sabal Trail? You didn’t do a very good job of demonstrating customers by dropping back to less than 2% Nom/Cap today. Did you break something? Again? Explain to us, FERC: why is this pipeline needed?

January 2018, Operational Capacity
January 2018

Also, FERC, if you did your job, we wouldn’t have to draw graphs like this. The best way to do your job would be to shut down Sabal Trail. Continue reading

Informational Postings: Transco, Sabal Trail, FSC, FGT, Gulfstream

Here are links to the FERC-required daily informational postings of the parts of the Southeast Markets Pipeline Project (SMPP), Transco, Sabal Trail, and FSC, plus the other two big natural gas pipelines into Florida: FGT and Gulfstream. Can somebody point me at any Duke Energy Florida (DEF) power plant that is not being fed by FGT or Gulfstream, now that DEF is no longer listed by Sabal Trail as a customer? And since FSC only lists its Martin County power plant, where are all those coal plants supposedly already- or to-be-modernized?

The Federal Energy Regulatory Commission (FERC) has a web page for Required Filers, which has a spreadsheet of Interstate Pipelines under the Natural Gas Act XLS updated 11/28/2017, but it’s incorrect, with the listing for Florida Southeast Connection going to the home page for NextEra Energy Resources. So, as usual, it’s necessary to do FERC’s job.


Transcontinental Pipeline Company (Transco)

Informational Postings and map.

Transco, Maps

Operationally Available. Perhaps most interesting is Continue reading

Sabal Trail admits Duke not customer, ramps up gas anyway 2018-01-04

Duke Energy Florida is no longer in the Customer Index in Sabal Trail’s FERC-required Informational Postings, as of January 1, 2018. Only Florida Power & Light is listed, still for 400,000 dekatherms per day. So what we’ve been saying since November appears to be true: Duke Energy Florida is no longer a Sabal Trail customer, which means there’s no excuse for Sabal Trail to have a Certificate of Convenience and Necessity, and FERC (or the D.C. Circuit Court) should revoke that permit.

Update 2018-01-05: Duke previously said it did NOT need Sabal Trail for the Crystal River power plant Duke is building, and in any case it could get the gas from Gulfstream or FGT if Sabal Trail failed, then Duke bought part of Sabal Trail, then Sabal Trail’s uncommitted capacity dropped by the same amount Duke was supposedly wanting, and now Duke is missing from Sabal Trail’s customer list. Plus most of Duke Energy Florida’s operational gas-fired power plants are being fed by FGT or Gulfstream, and apparently none from Sabal Trail.

Recent ramp in Sabal Trail gas, Postings

Yet Sabal Trail today just ramped up nominated capacity above operationally available capacity. Where’s that gas going, Sabal Trail? Continue reading

Motion to reject FERC DSEIS, to take Sabal Trail out of service, and to revoke its permit: WWALS to FERC 2017-12-29

reopen the whole basis of the FERC 2016 Order, Filing FERC, if it follows its own rules, should reject the DSEIS, stop Sabal Trail, and revoke its permit, says a motion filed today with FERC by Suwannee Riverkeeper.

Followup blog posts will feature major sections and arguments from these 20 pages with their 93 footnotes. The basic arguments are summarized on the first page:

WWALS argues that no SEIS can be complete without accounting for GHG from Liquid Natural Gas (“LNG”) exports, nor without comparing natural gas to solar power, according to precedents already set by FPL, FERC, and others, which also reopen the whole basis of the FERC 2016 Order.

FERC may not care, but the D.C. Circuit Court may, or candidates for office, or the voting public.

 -jsq, John S. Quarterman, Suwannee RIVERKEEPER®

You can join this fun and work by becoming a WWALS member today!


Filed with FERC today as Continue reading