Category Archives: LNG

FERC rubberstamps four rehearing denials and a new pipeline on a Friday 2018-08-10

Scurrying to use its rubberstamp before a Commissioner departing leaves it tied 2:2, FERC once again rubberstamped multiple pipelines, this time three on a Friday plus an LNG export project, while neither its main online library nor its backup library yielded copies of the orders.

I found these four by googling:

  • 164 FERC ¶ 61,099 Florida Southeast Connection, LLC Transcontinental Gas Pipe Line Company, Sabal Trail Transmission, Docket Nos. CP14-554-003, LLC CP15-16-004, LLC CP15-17-003, ORDER DENYING REHEARING, Issued August 10, 2018
  • 164 FERC ¶ 61,098, PennEast Pipeline Company, LLC, Docket No. CP15-558-001, ORDER ON REHEARING, August 10, 2018.
  • 164 FERC ¶ 61,100, Atlantic Coast Pipeline, LLC, Dominion Transmission, Inc., Atlantic Coast Pipeline, LLC, Piedmont Natural Gas Company, Inc., Docket Nos. CP15-554-002, CP15-555-001, CP15-556-001, Order on Rehearing, August 10 2018.
  • 164 FERC ¶ 61,102, Dominion Energy Cove Point LNG, LP, Docket No. CP17-15-001, ORDER DENYING REHEARING, August 10, 2018.

Oh, wait, a mention of a docket number in a FERC agenda leads me to one more Friday rubberstamp, of a new Transco pipeline in New Jersey:

FERC rubberstamp

  • 164 FERC ¶ 61,101, Transcontinental Gas Pipe Line Company, LLC, Docket No. CP17-490-000, ORDER ISSUING CERTIFICATE, August 10, 2018.

Commissioner Cheryl A. LaFleur dissented from Continue reading

FERC rubberstamps Sabal Trail time extension before filing it 2018-08-03

FERC filed its rubberstamp approval before filing Sabal Trail’s request for more time to finish its Suwannee County connection to FGT’s Jacksonville Expansion Project, which leads to Eagle LNG in Jacksonville, which can export liquid natural gas through Crowley Maritime. There’s no rubberstamp like the FERC rubberstamp.

FERC approval before Sabal Trail request, Docket CP15-17

FERC did delete the last “unpredictable” clause in this Sabal Trail sentence:

This coordination must occur while taking into account existing scheduled gas flows on each party’s respective system during the high demand of the summer cooling season, which makes the certainty by when this can occur unpredictable.

Since high seasonal demand has been touted as an excuse for this pipeline boondoggle, maybe FERC didn’t want to think about summer cooling season, “which makes the certainty by when this can occur unpredictable.”

We already saw last winter Sabal Trail couldn’t keep the gas flowing when it was so cold snow fell on Florida. Now Sabal Trail can’t finish construction because of summer heat.

You know what works find in the summer and winter sun? solar farms such as the one FPL is building right now 25 miles due north or that Duke already built about 55 miles northwest, both in Suwannee County, both by partners in Sabal Trail Transmission, LLC. Neither of those needed a FERC rubberstamp, because they didn’t need eminent domain. Continue reading

Farm Bureau pipeline and solar power policies 2018

Pipelines and rivers run through and by farms, and many farmers have solar panels, so it’s interesting to see what Farm Bureau has for energy policies.

Farm Bureau is for fixing FERC by revising the laws that let the Federal Energy Regulatory Commission reimburse Congress from fees and charges on the companies it supposedly regulates. Many of Farm Bureau’s pipeline policies are good and sound like it listened to Randy Dowdy. It gets hardcore about eminent domain. There are even a couple of items that, if law, would have been very useful in the recent and upcoming Sabal Trail eminent domain jury trials.

It has some very good solar energy policies, and it is for renewable energy, including incentives; even an electric car policy.

Not all is good. Farm Bureau is for “clean coal”, fracking, nuclear power, and oil and gas exploration everywhere. It never mentions wind power without mixing it with dirtier energy sources.

Title, Policy Book

This is all from FARM BUREAU® POLICIES FOR 2018: Resolutions on National Issues Adopted by the Voting Delegates of the Member State Farm Bureaus to the 99th Annual Meeting of the American Farm Bureau Federation®, Nashville, TN, January 2018.

Some of the policies are weirdly categorized: Continue reading

Benefits must outweigh harms –WWALS to FERC Re: Pipeline Certification NOI 2018-07-25

Here’s the WWALS response to FERC’s Notice of Inquiry (NOI) about “Certification of New Interstate Natural Gas Facilities”. A few excerpts:

FERC should approve no more pipelines without comparing not just coal plants to natural gas plants, but also comparing sun and wind power. If that means no more pipelines, so be it….

In one of the most egregious cases, Sabal Trail commenced construction on the land of the Bell Brothers in Mitchell County, Georgia, and when they countersued, Continue reading

Deadline for FERC rulemaking comments 2018-07-25

In addition to probably signing onto comments by a larger entity, WWALS is preparing comments for FERC in response to its Notice of Inquiry (NOI) about “Certification of New Interstate Natural Gas Facilities”. FERC’s current deadline is this Wednesday, 25 July 2018. Please send any suggestions you may have to wwalswatershed@gmail.com. Or file your own comments. Apologies for the late request.

Here’s what FERC has asked for:

In the NOI, the Commission sought input on whether, and if so how, the Commission should adjust: (1) its methodology for determining whether there is a need for a proposed project, including the Commission’s consideration of precedent agreements and contracts for service as evidence of such need; (2) its consideration of the potential exercise of eminent domain and of landowner interests related to a proposed project; and (3) its evaluation of the environmental impact of a proposed project. The Commission also sought input on whether there are specific changes the Commission could consider implementing to improve the efficiency and effectiveness of its certificate processes including pre-filing, post-filing, and post-order issuance.

South Georgia and north Florida
Sabal Trail through south Georgia and north Florida.
Map by Geology Prof. Can Denizman for WWALS.net, 17 September 2016, as part of Sabal Trail maps digitized.

Here are some relevant documents, starting with a how-to in case you want to file your own comments directly with FERC: Continue reading

Powelson leaves FERC with a split board as Sabal Trail loses legal cases 2018-07-02

Just one day before FERC admitted Sierra Club won in D.C. District Court, and a week after Sabal Trail Sabal Trail lost a jury trial in the U.S. Middle District of Georgia in Valdosta, something else at FERC put pause to further pipeline and LNG export rubberstamps.

Ellen M. Gilmer, Rod Kuckro and Sam Mintz, E&& News, 2 July 2018, Powelson’s departure means fallout for pipelines, policies,

Robert F. Powelson by FERC
Photo: FERC, of Robert F. Powelson, via E&E News

Robert Powelson’s decision to exit the Federal Energy Regulatory Commission less than a year into his term could leave natural gas pipeline developers in the lurch and policy critics scrambling for how to approach the commission’s coming 2-2 partisan split.

That’s the consensus among Continue reading

DoE FE can’t identify the circumstances for revoking an LNG export authorization

What sort of oversight can the U.S. Department of Energy (DoE) Office of Fossil Energy (FE) be performing for Liquid Natural Gas (LNG) export terminals when it says that: “DOE has stated that it ‘cannot precisely identify all the circumstances under which such action would be taken.’” Further:

DOE/FE has never rescinded a longterm non-FTA export authorization for any reason. Further, DOE has no record of ever having vacated or rescinded an authorization to import or export natural gas over the objections of the authorization holder.

This is all from a recent DoE article in the U.S. Federal Register, in which DoE manages to come up with only one example:

Louisiana LNG Energy LLC, in google cache
Louisiana LNG Energy LLC, in google cache

DOE has rescinded (or “vacated”) one long-term LNG export authorization to FTA countries (see supra note 2)—DOE/ FE Order No. 3482, issued to Continue reading

Landowner wins over Sabal Trail in jury trial, jsq on Scott James radio 2018-06-29

The just compensation for property takings required by the Fifth Amendment is not “just” compensation, said Scott James. And a jury of peers of a landowner told Sabal Trail to pay up five times what it offered for an easement for its fracked gas pipeline.

“…nor shall private property be taken for public use, without just compensation.”
—Fifth Amendment, U.S. Constitution

Scott said this jury award was big news and asked if it was just compensation. I said yes, front page in the Valdosta Daily Times.


VDT front page

And five times is more just than before. But how is a one-time payment Continue reading

WWALS prepares to sue FERC for shirking LNG Export oversight

Update 2022-07-26: You can comment or intervene on the Rulemaking on small inland Liquid Natural Gas (LNG) facilities that WWALS and six co-signers got started with FERC, the Federal Energy Regulatory Commission. We don’t need more methane leaks and we don’t need highly compressed explosive LNG trucks rolling down I-75 and I-10 with no environmental oversight and no safety plans.

FOR IMMEDIATE RELEASE

Washington, D.C., June 13, 2018 — WWALS Watershed Coalition (WWALS) prepares to sue the Federal Energy Regulatory Commission (FERC) for shirking its legally-required oversight of inland liquid natural gas (LNG) terminals. “LNG trucks barrel down I-75 right by my old high school in Lowndes County, Georgia,” said Suwannee Riverkeeper John S. Quarterman, after meeting with WWALS’ attorneys in Washington, D.C. “Those trucks from LNG terminals in Alabama and Georgia pass a technical college, a conference center, motels, homes, and businesses, going to I-10 for Jacksonville, Florida, where that LNG goes at least as far on ships as Puerto Rico.”

PDF flyer

Since the Federal Energy Regulatory Commission (FERC) in 2015 abdicated its jurisdictional duties under the Natural Gas Act to regulate the siting, construction, operation and maintenance of Liquefied Natural Gas (LNG) small-scale inland export facilities, instead these facilities operate with basically no Federal oversight.

“I am greatly concerned that an LNG commercial project of this magnitude is not only planned, but that apparently has slipped through the cracks of local and federal regulators,” said WWALS member Harriet Heywood of Citrus County, Florida.

At the ends of the Sabal Trail pipeline chain in Florida, trucks go out from half a dozen LNG export operations authorized by the U.S. Department of Energy Office of Fossil Energy (FE). If any of those trucks wrecks, federal standard everyone should be evacuated half a mile downwind, including high schools and hospitals. Very few local emergency responders know this and fewer have appropriate emergency plans.

 LNG Railcar Explosion, SE Cove Rd and SE Dixie Hwy, in Vulnerability of LNG by Rail, <br/>by Martin County Fire Rescue, December 15, 2015.” /></a><br />
LNG Railcar Explosion, SE Cove Rd and SE Dixie Hwy, in <a href=Vulnerability of LNG by Rail, by Martin County Fire Rescue, December 15, 2015.

“The unintended consequences of FERC’s abdication of Congressional jurisdictional authority are mind-boggling,” said WWALS member Cecile Scofield of Palm City, Martin County, Florida, “They include Continue reading

Fundraiser to stop FERC shirking LNG oversight

Update 2022-10-26: WWALS response to opposition comments by Eagle LNG about small, inland LNG 2022-10-17.

Update 2022-10-04: WWALS response to FERC on opposition comments of Pivotal LNG about small, inland LNG Rulemaking 2022-10-04.

Update 2022-07-26: You can comment or intervene on the Rulemaking on small inland Liquid Natural Gas (LNG) facilities that WWALS and six co-signers got started with FERC, the Federal Energy Regulatory Commission. We don’t need more methane leaks and we don’t need highly compressed explosive LNG trucks rolling down I-75 and I-10 with no environmental oversight and no safety plans.

Update 2022-07-22: Petition for Rulemaking on FERC Oversight of Small-Scale Inland LNG Export Facilities 2022-07-22.

Update 2021-07-21: Ghost company: Strom LNG.

Update 2018-11-14: Strom Inc. export through Tampa, Map And Strom wants to export through Port of Tampa, on tanker ships under the I-275 bridge right past St. Pete.

Update 2018-06-13: Press Release.

The Federal Energy Regulatory Commission (FERC) has abdicated its jurisdictional duties under the Natural Gas Act to regulate the siting, construction, operation and maintenance of Liquefied Natural Gas (LNG) small-scale inland export facilities.

Instead these facilities operate with basically no Federal oversight.

LNG trucks barrel down I-75 through Georgia past high schools, colleges, businesses, and homes, then on I-10 to Jacksonville for ships at least as far as Puerto Rico. At the ends of the Sabal Trail pipeline chain in Florida, trucks go out from half a dozen LNG export operations authorized by the U.S. Department of Energy Office of Fossil Energy (FE). If any of those trucks wrecks, federal standard everyone should be evacuated half a mile downwind, including high schools and hospitals. Very few local emergency responders know this and fewer have appropriate emergency plans.

LNG export routes, Map
Map: by WWALS, from federal and state filings of LNG export operations.

Compounding the problem, Continue reading