Tag Archives: John Peconom

Sabal Trail shakey gas flow and Phase II 2019-06-11

Apparently some people in Albany, GA and Dunnellon, FL were surprised when Sabal Trail a week ago sent FERC “Notice of Commencement of Construction – Phase II Sabal Trail Project Facilities”, which means for the compressor stations in those two locations. But that notice was merely that “bona fide construction activities commenced on May 29, 2019.” FERC rubberstamped Phase II back in January, and Sabal Trail has been reporting on site clearing, gravelling, etc. for months.

[Aerial]
Albany Compressor Station site Aerial from 2019-01-17 STT filing

Meanwhile, Sabal Trail still can’t keep the gas flowing through its stranded asset pipelines. There never was any “need” for that gas in Florida, where Florida Power & Light (FPL)’s customers are stuck with the $4 billion construction bill. While FPL’s parent NextEra Energy never mentions Sabal Trail any more. NextEra brags instead about being a world leader in solar and wind energy.

[All (2017-06-14--2019-06-11)]
All (2017-06-14 — 2019-06-11)

When John Peconom of the Federal Energy Regulatory Commission (FERC) inked that rubberstamp back in January, the schedule was Continue reading

Sabal Trail Phase II: Albany and Dunnellon Compressor Stations 2019-01-17

FERC being short a Commissioner does not stop the rubberstamp machine, this time for the Albany, GA, and Dunnellon, FL, Compressor Stations, both to start construction in May 2019. Sabal Trail requested Phase II in mid-January, and FERC’s John Peconom authorized it by the end of the month.

[Project Location Map]
Project Location Map
PDF

2019-01-17 Request

Continue reading

FERC rubberstamped Suwannee M&R Station and Sabal Trail already built it 2019-02-11

FERC took less than a week to rubberstamp Sabal Trail’s first of February request, and Sabal Trail took less than a week after that to put the Metering and Regulation Station in service, connecting to Florida Gas Transmission in Suwannee County, Florida, onwards under the proposed phosphate mine site in Union and Bradford Counties, to Jacksonville, where Eagle LNG and Crowley Maritime’s Carib Energy are already sending LNG at least as far as Puerto Rico. Do the “applicable remaining terms and conditions of the Orders” include not leaking, like Sabal Trail already did at its nearby compressor station?

[3.4 miles, Hildreth Compressor Station to Suwannee M&R]
3.4 miles, Hildreth Compressor Station to Suwannee M&R; see also Google map.

Sabal Trail wants last Phase 1 facility in service: Suwannee M&R Station 2019-02-01

In case you thought it was over, or that a September 2018 leak or death of a FERC Commissioner might have slowed down FERC’s rubberstamp, Sabal Trail wants to finish Phase I construction by firing up gas through its Suwannee Metering & Regulation (M&R) station.

[Suwannee M&R Detail]
Suwannee M&R Detail, from Sabal Trail Alignment Map 1657-PL-DG-70197-305, courtesy Lowndes Area Knowledge Exchange (LAKE).

FERC’s rubberstamp will feed gas to Florida Gas Transmission (FGT), onwards under the proposed HPS II phosphate mine in Union and Bradford Counties, to Jacksonville, apparently to feed Eagle LNG, which is already shipping gas as far as Puerto Rico, through Crowley Maritime, which has authorization from U.S. DoE Office of Fossil Energy to export liquid natural gas (LNG) to all Free Trade Agreement (FTA) and non-FTA countries; see LNG. Continue reading

Sabal Trail, WWALS, OSFR’s Merrillee Malwitz-Jipson, and FERC’s John Peconom in Jasper, FL 2014-10-21

Four years ago Merrillee Malwitz-Jipson set the festive tone outside a special Sabal Trail Open House:

Merrillee Malwitz-Jipson and family, Open House
Photo: John S. Quarterman, the family that demonstrates together stays together: “No pipeline in springs heartland” and “No pipeline in my future” and “Stop fossil fuel production”.

Merrillee has been in the thick of opposing fossil fuel boondoggles and promoting clean solar power since at least 2013.

Why was this one of only two Sabal Trail Open Houses in fall 2014, way back when FERC’s John Peconom actually answered when any of us called? Continue reading

State and local responses to Dunnellon Sabal Trail stink

Sabal Trail did not notify state or local officials about their “odorant” leak at the Dunnellon Compressor Station site, and Sabal Trail’s response to WWALS failed to mention local people called the same stink in to 911 two days in a row. FDEP said there’s no need so long as Sabal Trail follows various permits, but gave no indication of who is checking to see if Sabal Trail does that. Apparently we the people have to keep doing what the state and federal agencies still aren’t doing: watch Sabal Trail like a hawk.

Via FL 200
Google map of locations of Dunnellon High School and Sabal Trail Dunnellon Compressor Station. You can see most of the 100-foot Sabal Trail right of way.

Below are responses from FDEP and more details from Marion County Public Relations and Fire and Rescue, and from Dunnellon Fire and Rescue: none of them were notified by Sabal Trail, and FDEP seems OK with that. For the rest, an emergency plan would be prudent: “Run like hell” as in Spectra compressor station incidents elsewhere, is probably not adequate. Continue reading

Enbridge about Sabal Trail stinks 2017-07-28

No gas leak, just a stink leak, said Spectra Energy’s new owner Enbridge in an emailed response yesterday to the WWALS 19 questions about the Dunnellon Compressor Station leak.

Stink tanks
These are apparently the “two odorant tanks and equipment” mentioned by Sabal Trail, visible from FL 200.

That response was no more substantive than we used to get in the bi-weekly reports: no indication of who notified Sabal Trail; no indication that they worked on it more than one day, even though multiple witnesses attest to that; no indication of who Sabal Trail notified, if anybody; no indication of what they were doing working in a different part of the site a week later when I took the pictures in the WWALS submission; no answer as to whether they are feeding methane to the Citrus County Pipeline; etc.

The responses from FERC and from USACE are the same as usual: nothing at all. We did get a reply from FDEP; more on that in a later post.

Previously Sabal Trail has provided its non-answers to WWALS and others in Continue reading

Drilling mud oozing up into the Withlacoochee River from Sabal Trail HDD

Update 2016-11-14: GWC Dirty Dozen Press Conference at US 84 Bridge with tour of Sabal Trail HDD 2016-11-16

Update 2016-11-13:Sabal Trail still leaking drilling mud into the Withlacoochee River at US 84 in GA 2016-11-12

FOR IMMEDIATE RELEASE

Hahira, GA, November 11th 2016 — Sabal Trail leaked drilling mud up from their HDD pilot hole into the Withlacoochee River. Turbidity curtains and black pipe from the north bank They knew this before WWALS asked two weeks ago what is that yellow thing in the river? They did not tell WWALS or the public that this thing they testified could not happen did happen. The evidence is in writing from Sabal Trail’s contractor to the Georgia Environmental Protection Division.

This wasn’t even the actual horizontal directional drilling (HDD) borehole: it was just the smaller pilot hole. What will happen to the Withlacoochee River (or nearby water wells) with the main borehole? What will happen to the Ochlockonee River west of Moultrie, GA? What will happen to the Santa Fe River, where Sabal Trail is drilling now, or the Suwannee River, where it will drill soon, both Outstanding Waters of Florida, supposed to have extra measures of environmental protection? What about the Tallapoosa, Chattahoochee, or the other Withlacoochee (south) River?

“Why should we accept any risk to our waters, or eminent domain to take our lands, for an unnecessary pipeline, now that Continue reading

What is Sabal Trail sending into the WIthlacoochee River between Quitman and Valdosta, GA? WWALS PR 2016-11-09

Update 2016-11-14: GWC Dirty Dozen Press Conference at US 84 Bridge with tour of Sabal Trail HDD 2016-11-16

Update 2016-11-13:Sabal Trail still leaking drilling mud into the Withlacoochee River at US 84 in GA 2016-11-12

Update 2016-11-11: Sabal Trail leaked drilling mud up into the Withlacoochee River.

FOR IMMEDIATE RELEASE

Hahira, GA, November 9th 2016 — Sabal Trail appears to have contradicted itself in its recent responses to WWALS, perhaps admitting it may be dumping drilling mud into the Withlacoochee River, which would explain the picture below of a black pipe coming from Sabal Trail’s Brooks County HDD site into the river. WWALS had to wait two weeks just to get those non-answers, so WWALS now asks for a written response by email tomorrow. In addition, at least two Sabal Trail yards (a contractor yard in Moultrie, GA and a pipe yard near Lake City, FL) appear never to have been approved by FERC.

Dumping
About 2000 feet upstream (north) of the US 84 bridge. Many more pictures here.

“FERC granted permission in less than a week for Continue reading

Non-answers in Sabal Trail Biweekly Status Report 2016-11-04

If drilling mud may be released, how can this also be? “No wastewater has been or will be dumped into the Withlacoochee River.” Sabal Trail seems to have contradicted itself. Sabal Trail responses to WWALS questions And didn’t answer the permit questions from WWALS. Nonetheless all their responses are marked “Resolution Date: 10/30/2016”. Nope, not resolved, Sabal Trail. See new questions.

Sabal Trail also said (see the PDF) it was completing drilling under the Flint River, was drilling under the Ochlockonee and Withlacoochee Rivers in Georgia, had just started under the Santa Fe River, was doing clearing and pad preparation for the Chattahoochee and Suwannee Rivers, and hadn’t yet started anything at the Withlacoochee (south) River in Florida. Plus quite a few complaints and questions, including some from FERC, and some archaeological discoveries which Sabal Trail and FERC hid under “Privileged and Confidential information”.

The Sabal Trail responses labeled Continue reading