Tag Archives: Southeast Markets Pipeline Project

FERC rubberstamps four rehearing denials and a new pipeline on a Friday 2018-08-10

Scurrying to use its rubberstamp before a Commissioner departing leaves it tied 2:2, FERC once again rubberstamped multiple pipelines, this time three on a Friday plus an LNG export project, while neither its main online library nor its backup library yielded copies of the orders.

I found these four by googling:

  • 164 FERC ¶ 61,099 Florida Southeast Connection, LLC Transcontinental Gas Pipe Line Company, Sabal Trail Transmission, Docket Nos. CP14-554-003, LLC CP15-16-004, LLC CP15-17-003, ORDER DENYING REHEARING, Issued August 10, 2018
  • 164 FERC ¶ 61,098, PennEast Pipeline Company, LLC, Docket No. CP15-558-001, ORDER ON REHEARING, August 10, 2018.
  • 164 FERC ¶ 61,100, Atlantic Coast Pipeline, LLC, Dominion Transmission, Inc., Atlantic Coast Pipeline, LLC, Piedmont Natural Gas Company, Inc., Docket Nos. CP15-554-002, CP15-555-001, CP15-556-001, Order on Rehearing, August 10 2018.
  • 164 FERC ¶ 61,102, Dominion Energy Cove Point LNG, LP, Docket No. CP17-15-001, ORDER DENYING REHEARING, August 10, 2018.

Oh, wait, a mention of a docket number in a FERC agenda leads me to one more Friday rubberstamp, of a new Transco pipeline in New Jersey:

FERC rubberstamp

  • 164 FERC ¶ 61,101, Transcontinental Gas Pipe Line Company, LLC, Docket No. CP17-490-000, ORDER ISSUING CERTIFICATE, August 10, 2018.

Commissioner Cheryl A. LaFleur dissented from Continue reading

FERC and Sabal Trail admit Sierra Club won 2018-07-03

One week after losing a jury trial in the U.S. Middle District Court of Georgia, the Sabal Trail fracked methane pipeline and its purveyor of federal eminent domain, the Federal Energy Regulatory Commission (FERC), declined to appeal their huge DC District Court loss of last August.

Sierra Club, Press Release, 3 July 2018, Fracked Gas Pipeline Company and Federal Regulator Will Not Seek Supreme Court Review of Landmark Ruling: Existing Decision Means FERC Must Consider Downstream Greenhouse Gas Emissions,

WASHINGTON, D.C. — Neither the builders of the fracked gas Sabal Trail Pipeline nor the Federal Energy Regulatory Commission (FERC) will ask the Supreme Court to review a landmark ruling by the U.S. Court of Appeals for the District of Columbia Circuit from last year. That decision required FERC to consider the effects of downstream greenhouse gases when deciding whether to approve proposed pipelines that transport gas.

In response, Sierra Club Staff Attorney Elly Benson released the following statement:

Elly Benson, Sierra Club Attorney
Elly Benson, Sierra Club Staff Attorney

“We are glad to see FERC accept its responsibility to consider greenhouse gas emissions from burning transported gas at downstream power plants. These dirty, dangerous, and unnecessary pipelines pose a threat to our communities and climate. They should not be proposed, much less built, at a time when clean, renewable energy sources are abundant and affordable. We will continue to monitor the pipeline permitting process to ensure the law is followed.”

The pipeline industry press was not thrilled. Charlie Passut, Natural Gas Intelligence, 5 July 2018, FERC Declines to Appeal Landmark GHG Case to Supreme Court, Continue reading

FPL wants Martin-Riviera Pipeline folded into FSC

Update 2019-03-11: And of course FERC and FPSC approved it, this extension of FSC to within 300 feet of an LNG export port.

What is FPL hiding in all that confidential and redacted material in a 117-page petition for approval of folding FPL’s Martin-Riviera Pipeline into Sabal Trail’s downstream Florida Southeast Connection (FSC)? This has been planned at least two years. on the excuse of lower rates for customers. Yet FPL redacted what FSC would charge and future cost projections, so FPL’s customers and the rest of the public affected by these unnecessary pipelines have no way of knowing what they would cost, and emergency responders can’t see what’s on this pipeline.

Indiantown to Riviera Beach
Indiantown to Riviera Beach, in FERC 20180309-5230, Docket CP18-108.

Eagle-eye WWALS member Janet Barrow spotted this Florida Public Service Commission (FPSC) Docket 20170231 (OPEN) — Petition for approval to transfer Martin- Riviera Lateral Pipeline to Florida Southeast Connection and implement associated rate adjustments, by Florida Power & Light Company.

FPSC let FPL redact most anything it wanted to, in Continue reading

Informational Postings: Transco, Sabal Trail, FSC, FGT, Gulfstream

Here are links to the FERC-required daily informational postings of the parts of the Southeast Markets Pipeline Project (SMPP), Transco, Sabal Trail, and FSC, plus the other two big natural gas pipelines into Florida: FGT and Gulfstream. Can somebody point me at any Duke Energy Florida (DEF) power plant that is not being fed by FGT or Gulfstream, now that DEF is no longer listed by Sabal Trail as a customer? And since FSC only lists its Martin County power plant, where are all those coal plants supposedly already- or to-be-modernized?

The Federal Energy Regulatory Commission (FERC) has a web page for Required Filers, which has a spreadsheet of Interstate Pipelines under the Natural Gas Act XLS updated 11/28/2017, but it’s incorrect, with the listing for Florida Southeast Connection going to the home page for NextEra Energy Resources. So, as usual, it’s necessary to do FERC’s job.


Transcontinental Pipeline Company (Transco)

Informational Postings and map.

Transco, Maps

Operationally Available. Perhaps most interesting is Continue reading

Motion to reject FERC DSEIS, to take Sabal Trail out of service, and to revoke its permit: WWALS to FERC 2017-12-29

reopen the whole basis of the FERC 2016 Order, Filing FERC, if it follows its own rules, should reject the DSEIS, stop Sabal Trail, and revoke its permit, says a motion filed today with FERC by Suwannee Riverkeeper.

Followup blog posts will feature major sections and arguments from these 20 pages with their 93 footnotes. The basic arguments are summarized on the first page:

WWALS argues that no SEIS can be complete without accounting for GHG from Liquid Natural Gas (“LNG”) exports, nor without comparing natural gas to solar power, according to precedents already set by FPL, FERC, and others, which also reopen the whole basis of the FERC 2016 Order.

FERC may not care, but the D.C. Circuit Court may, or candidates for office, or the voting public.

 -jsq, John S. Quarterman, Suwannee RIVERKEEPER®

You can join this fun and work by becoming a WWALS member today!


Filed with FERC today as Continue reading

Nine Riverkeepers say FERC’s Sabal Trail SEIS unacceptable; request pipeline shutdown

FOR IMMEDIATE RELEASE

Hahira, Georgia, November 21, 2017 — Factually incorrect, failing to account for LNG export or solar power, and irresponsible for not finding or creating a method for attributing environmental effects to greenhouse gases, as the DC Circuit Court had instructed the Federal Energy Regulatory Commission (FERC) to do: that’s what nine Riverkeepers called FERC’s Supplementary Environmental Impact Statement (SEIS) yesterday; see their letter to FERC. The nine include all the Riverkeepers in the path of Sabal Trail and all parts of the Southeast Market Pipelines Project (SMPP) plus others in all three states invaded by those pipelines, Florida, Georgia, Alabama, plus Oklahoma, where the SMPP instigator, Florida Power & Light (FPL), owns a fracking field, The nine, who support fishable, swimmable, drinkable water, pointed out that all of FPL’s original excuses for Sabal Trail have been proven incorrect, and asked FERC to shut it down.

Green is Sabal Trail; Transco and FSC in black, SMPP
Sabal Trail in green, Transco and FSC in black, in Sierra Club interactive map of gas pipelines.

The Riverkeepers weren’t buying FERC’s ignorance: Continue reading

Eight Riverkeepers oppose FERC’s inaccurate and inadequate Sabal Trail SEIS and request pipeline shutdown 2017-11-20

Filed today as FERC Accession number 20171120-5130, “Opposition to the incorrect and inadequate FERC Sabal Trail SEIS and request for pipeline shut down by Suwannee Riverkeeper (WWALS) and Apalachicola, Ogeechee, Grand, Choctawhatchee, Chattahoochee, Indian, and Flint Riverkeepers.” (Or see WWALS PDF.)

Shut it down, From: The undersigned Waterkeepers

Date: November 20, 2017

To: Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
888 First Street NE, Room 1A
Washington, DC 20426

Re: We oppose the incorrect and inadequate FERC Sabal Trail SEIS
FERC Docket Numbers CP14-554-002, CP15-16-003, and CP15-17-002

On September 27, 2017, the Federal Energy Regulatory Commission (FERC) published a draft Supplementary Environmental Impact Statement (SEIS).[1] That SEIS was in response to the August 27, 2017 DC Circuit Court decision[2] regarding FERC’s previous approval of Certificates of Convenience and Necessity for the three parts of the Southeast Markets Pipeline Project (SMPP), which are the Transcontinental Gas Pipe Line Company, LLC’s (Transco) Hillabee Expansion Project in Docket No. CP15-16-000; Sabal Trail Transmission, LLC’s (Sabal Trail) Sabal Trail Project in Docket No. CP15-17-000; and Florida Southeast Connection, LLC’s (FSC) Florida Southeast Connection Project in Docket No. CP14-554-000. The judges ordered:

“The orders under review are vacated and remanded to FERC for the preparation of an environmental impact statement that is consistent with this opinion.“

The draft SEIS issued by FERC is clearly not consistent with the court’s opinion for the following reasons:

  1. The SEIS is factually incorrect in stating that: Continue reading

From pipelines to renewable energy and efficiency –Sierra Club 2017-08-29

“Once the court officially returns the matter to FERC, the pipeline should cease operations while FERC undertakes the new analysis,” wrote Elly Benson, lead attorney for the case Sierra Club just won against Sabal Trail.

She summed up: ”Instead of sacrificing our communities and environment to build unnecessary pipelines that “set up surefire profits” for pipeline companies at the expense of captive ratepayers, the focus should be on transitioning to clean renewable energy and energy efficiency—especially in the Sunshine State. Forcing federal agencies to grapple with the true climate impacts of dirty fossil fuel projects is a big step in the right direction.”

She leads off this fourth in a WWALS news roundup series (1, 2, 3) about that case, followed by Gordon Rogers, Flint Riverkeeper, another party to the case.

WWALS is not a party to that case and does not speak for the parties, so I can be a cheerleader for them. Shut it down! Let the sun rise!

How many pipelines do we want? None! When do we want it? Never!
How many pipelines do we want? None! When do we want them? Never! —WWALS at the Sabal Trail Suwannee River crossing, 15 August 2015.

This is wind in our sails and could be the end of Sabal Trail –Suwannee Riverkeeper in VDT 2017-08-24

Update 2017-08-29: Fourth news roundup: From pipelines to renewable energy and efficiency –Sierra Club 2017-08-29

“This is wind in our sails and could be the end of Sabal Trail,” Quarterman said, on the front page of the newspaper of record in the largest city in the Suwannee Basin, the Valdosta Daily Times.

Heading downstream
We got sails no one can see.
Suwannee Riverkeeper Vessel on the Suwannee River protesting Sabal Trail 2017-01-14

As Frank Jackalone says (see below), FERC has been getting away with murder. And now maybe they can’t.

Thomas Lynn, Valdosta Daily Times, 23 August 2017, Court decision to impact Sabal Trail pipeline, Continue reading

Pipeliners spooked by Sierra Club Major Landmark Victory; could shut down Sabal Trail –industry press

Update 2017-08-29: Fourth news roundup: From pipelines to renewable energy and efficiency –Sierra Club 2017-08-29

Update 2017-08-24: Third news roundup: This is wind in our sails and could be the end of Sabal Trail —Suwannee Riverkeeper in VDT 2017-08-24

OilPrice.com calls it “a critical decision yesterday, that could jeopardize the future for pipeline projects across the country”; pipeline companies could be “spooked” and “…the court ruling raises the unsettling possibility that the project may be forced to shut down — after billions were spent putting it in into service.” Other stories say this ‘huge’ win could also affect the Atlantic Sunrise, Penneast, Atlantic Coast, and Rover Pipelines, among others.

Children against Sabal Trail in Juno Beach, 2016-10-14
(L to R) Lea Fox, 4, Finn Ryder Purdy, 4, and Mason Dana, 7, of Lake Worth, sit with gas pipeline protesters outside of Florida Power and Light headquarters on Universe Boulevard in Juno Beach on October 14, 2016. The Sabal Trail Pipeline began supplying FPL’s plants in June. Groups opposed the pipeline that will start in Alabama and bring fracked gas through several counties in Florida’s springs and wetlands. (Richard Graulich / The Palm Beach Post)

Sad for FPL, Duke, Spectra, and all the other pipeline-building purveyors of fracked methane, maybe, but glad for all the landowners whose land was taken, local citizens who don’t want a 500+-mile IED next to their homes, schools, and waterways, and all people who want clean sun and wind energy, not more polluting fossil fuels.

It’s good the industry press agrees with what I told the VDT: “This is wind in our sails and could be the end of Sabal Trail.”

Here’s a news roundup, in addition to Continue reading