Tag Archives: hearing

Comment now: TPM mine drains to Okefenokee Swamp, Rivers Styx, St. Marys, Suwannee, Georgia and Florida 2020-04-10

Comment by this Monday, April 13, 2020, if you don’t want any of these creeks, rivers, or the Okefenokee Swamp affected by this strip mine, or the Floridan Aquifer, in Georgia or in Florida.

The Twin Pines Minerals strip mine site drains west from Trail Ridge into the River Styx, into the Okefenokee Swamp, and to the St. Marys River, which becomes the border between Georgia and Florida. On the east, it drains into Boone Creek and into the St. Marys River. If it affects the Swamp, it will affect the Suwannee River, which runs through Georgia and Florida to the Gulf of Mexico.

[River Styx]
River Styx

Please go ahead and tell the U.S. Army Corps of Engineers why you don’t want this strip mine near the Swamp.

You can also ask for an extension of the public comment deadline, and for public hearings in Georgia and Florida. Here is the Suwannee Riverkeeper extension and hearings request for WWALS.

The Rule the Corps is following for comments says the U.S. Environmental Protection Agency (EPA) can require any other affected state to comment. So you can ask EPA to ask Florida to comment. Here is our request for that. Here’s a simple version you can use:

[Your Name or Your Organization Name] requests the U.S. Environmental Protection Agency (EPA), pursuant to 33 CFR § 325.2, (b), regarding permit application SAS-2018-0054 to determine that the mining activities of the subject Application may affect the quality of the waters of the state of Florida and to notify the state of Florida, the district engineer, and the applicant that Florida ‘has 60 days from receipt of EPA’s notice to determine if the proposed discharge will affect the quality of its waters so as to violate any water quality requirement in such state, to notify EPA and the district engineer in writing of its objection to permit issuance, and to request a public hearing.’

The inset map is from Figure 66 in the TPM application. TPM didn’t label the waterways, but that’s the River Styx where it says MSW-1, and Boone Creek where it says MSW-4. Both lead to the St. Marys River, which becomes the Georgia-Florida state line. The River Styx joins the St. Marys in the Okefenokee Swamp, which is the headwaters of the Suwannee River. Continue reading

Two thirds of SRWMD Board half there 2019-09-18

It was surprisingly interactive meeting, with the Board members repeatedly questioning staff about multiple projects, sometimes taking up points raised from the audience. One Board Member even stopped a project. Yet half the rump board was not visible, being on the telephone, and the Budget Public Hearing may or may not have been legal.

Nestlé Water Withdrawal Permits

At the rescheduled September SRWMD Board meeting, OSFR President Mike Roth questioned the validity of the permitting process for Nestlé’s proposed 1.2 million gallon per day water withdrawal from Ginnie Springs on the Santa Fe River, since the actual application is from Seven Springs, which proposes to sell the water to Nestlé, which is not a use authorized by Florida Statutes.

[OSFR President]
OSFR President

I seconded that, and added that the SRWMD Board should revisit Nestlé’s permit for water withdrawal at Madison Blue Springs on the Withlacoochee River, since Florida Statutes to authorize them to do that.

You can comment to SRWMD about Nestlé’s permits.

Photo: Jim Tatum for OSFR, of Suwannee Riverkeeper John S. Quarterman
Photo: Jim Tatum for OSFR, of Suwannee Riverkeeper John S. Quarterman

Afterwards, SRWMD’s Tom Mirti told me the $70,000 contract with SRWMD for Nestlé to support springs water quality monitoring is required by the Nestlé permit for Madison Blue Spring, even though it has to be negotiated separately. Apparently yet another open records request is needed.

Invisible and Missing Board Members

Continue reading

Bradford BOCC 2018-09-04

All the public speakers were against the phosphate mine. Before the Commissioners decided, Merrillee Malwitz-Jipson spoke about rain, the Chemours mine, and how what Bradford County does affects her business downstream. (I think Stasia Rudolph also spoke before I got there.) After some confusion on timing, afterwards Marc Lyons reminded them Citizens Against Phosphate Mines (CAPM) is ready to sue, and Kate Ellison said she hopes this means we will all see the consultant’s report before the public hearings. I sent a letter and a resolution the previous day and gave them paper copies.

The actual decision was much better than expected. While some Commissioners wanted to hold Continue reading

Sabal Trail violations FDEP assured us would not happen are happening

Already under the Withlacoochee River in Georgia there’s been a frac-out and a sinkhole at a drilling site, upstream from the Suwannee River in Florida, under which FDEP told us it couldn’t happen:

Lisa Prather, sole FDEP witness Well, the Suwannee River crossing doesn’t, in fact, have any impacts to an outstanding Florida water….”

“Well, any work within, or could have adverse effects on OFW, is considered. In this case, we determine that there would be no impacts to the OFW.

Apparently not only FDEP’s sole witness Lisa Prather believed Sabal Trail; according to a video yesterday by Cody Suggs at the Suwannee River, Sabal Trail’s own workers seem to believe their company’s propaganda.

Much more about WWALS v Sabal Trail & FDEP is on the WWALS website, including videos and transcripts of the landowners who also tried to warn FDEP that sinkholes happen like they already have including under at least two public roads in Suwannee County, Florida. And more about what already happened is on the WWALS website, plus things you can do to stop this $3 billion dollar fracked methane boondoggle.

For example, you may want to ask the permitting agencies some of the questions WWALS asked, including this one:

Which of FERC, FDEP, GA-EPD, USACE, SRWMD are working to protect the health, welfare and safety of the communities surrounding this pipeline and how are they doing that?

Given that I asked them for a prompt answer and two weeks later have gotten no answer at all, it sure looks like we the people will have to find and report violations and use other methods to stop this pipeline.

The transcript questions quoted below are Continue reading

Judge assigned for WWALS v. Sabal Trail and FL-DEP

Here’s the letter DOAH sent Friday 4 September 2015 that we received on paper yesterday. Fortunately, it’s also online along with the rest of Case No: 15-004975. It’s been assigned Judge Bram D. E. Canter.

STATE OF FLORIDA
DIVISION OF ADMINISTRATIVE HEARINGS

 
 
 
Case No. 15-4975
15-0468

 
WWALS WATERSHED COALITION, INC.,

      Petitioner,

vs.

SABAL TRAIL TRANSMISSION. LLC AND
DEPARTMENT OF ENVIRONMENTAL PROTECTION,

      Respondent.
/

INITIAL ORDER

Initial Order
  1. Any document filed with DOAH by a party represented by an attorney shall be filed by electronic means through eALJ located at www.doah.state.fl.us. Parties not represented by an attorney may file by electronic means through eALJ. Any document filed through eALJ shall include the filing party’s e-mail address and be served upon all other parties. All pleadings and motions must contain the DOAH style and case number.
  2. THE AGENCY OR, WHERE THE AGENCY IS NOT A PARTY, THE PETITIONER SHALL COORDINATE WITH ALL PARTIES AND PROVIDE THE FOLLOWING INFORMATION WITHIN SEVEN DAYS Continue reading

A hearing for WWALS v Sabal Trail after all –WCTV

The hearing will be about the Suwannee River in Florida, and the same pipeline wants to cross the Withlacoochee River in Georgia (and the Ochlockonee, Flint, and Chattahoochee in Georgia, and the Santa Fe and the other Withlacoochee River in Florida).

Winnie Wright, WCTV, 4 September 2015, WWALS Receives Hearing on Sabal Trail Pipeline,

JASPER, Fla. — The WWALS will receive a hearing regarding the Sabal Trail Pipeline, according to the group.

“Everyone told us we’d never get a hearing, so apparently we interpreted the previous day’s FL-DEP dismissal too broadly. But sometimes if you try, you succeed. And WWALS continues to try to stop the unnecessary, destructive, and hazardous Sabal Trail pipeline,” said Continue reading

Florida state regulators grant hearing at unknown data for WWALS v. Sabal Trail –Palm Beach Post

You’ve mostly been hearing about WWALS v. Sabal Trail lately because of all the news coverage related to the petition to FL-DEP, which is great. STA. 13083+00 TO STA. 13136+00, GA-FL Line, Hamilton Co., FL, Jumping Gulley Creek But of course WWALS does a lot more than that and WWALS has been around before anybody ever heard of Sabal Trail.

Susan Salisbury, Palm Beach Post, 4 September 2015, State regulators grant hearing to anti-pipeline group,

WWALS Watershed coalition and WWALS-Florida which advocate for conservation of Suwannee River and other rivers in south Georgia and North Florida believe the proposed pipeline is not in the public interest and could have severe adverse effects on fish, wildlife, public recreation and navigation.

The pipeline would also go through the fragile karst limestone containing Continue reading

WWALS to get hearing against Sabal Trail after all –Gainesville Sun

WWALS is about environmental issues such as those FL-DEP said could proceed. However, environmental issues extend far beyond FL-DEP’s narrow view. A pipeline sinkhole could affect springs or wells miles away, and that could affect property values, insurance rates, and of course eco-tourism. Tourism brings in $67 billion a year to Florida. Why would any Florida state agency want to risk that for a pipeline when the Sunshine State can go straight to solar power?

Christopher Curry, Gainesville Sun, 4 September 2015, Part of Sabal Trail challenge will proceed, Continue reading

FL-DEP grants hearing to WWALS against Sabal Trail pipeline under Suwannee River

FOR IMMEDIATE RELEASE

FL-DEP grants hearing to WWALS against Sabal Trail pipeline under Suwannee River

September 4nd, 2015, Jasper, Florida — Yesterday the Florida Department of Environmental Protection (FL-DEP) asked for an administrative law judge (ALJ) “to conduct all necessary proceedings required by law and to submit a recommended order to the Department”. Certifiate of Service FL-DEP apparently interprets its Order of the previous day as dismissing only the petition of WWALS-FL, a Florida nonprofit corporation, and not that of the parent corporation, WWALS Watershed Coalition, Inc. (WWALS). So it seems WWALS gets a hearing after all.

WWALS president John S. Quarterman remarked:

“Everyone told us we’d never get a hearing, so apparently we interpreted the previous day’s FL-DEP dismissal too broadly. But sometimes if you try, you succeed. And WWALS continues to try to stop the unnecessary, destructive, and hazardous Sabal Trail pipeline.”

And it seems FL-DEP is reading the news about this case, because Continue reading

WWALS to get hearing with FL-DEP about Sabal Trail –Palm Beach Post

FL-DEP is reading the news about the WWALS petition, we know because DEP sent a copy of yesterday’s FL-DEP request for an administrative law judge directly to the Palm Beach Post. The Post had already published a story saying the WWALS petition had been dismissed, and changed it to say WWALS has been granted a hearing. (See also WWALS press release.)

Susan Salisbury, Palm Beach Post, 3 September 2015, Florida DEP says anti-pipeline group’s case to be heard,

A conservation group seeking to stop the proposed 465-mile Sabal Trail natural gas pipeline from boring under the iconic Suwannee River has now been granted its request for a hearing.

The Florida Department of Environmental Protection said late Thursday Continue reading